<regulation prefix="Regulation" num=".01" citation="COMAR 26.13.07.01" title_num="26" subtitle_num="13" chapter_num="07" heading="Permit Required.">
  <paragraph num="A.">
    <text>Except for persons identified in COMAR 26.13.05.01 A(3) or D, 26.13.06.01A(4) or (5), or 26.13.07.23A(1), a person may not operate any facilities without first obtaining a valid CHS permit from the Department. A CHS permit will not be issued without the facility first having applied for an EPA identification number.</text>
  </paragraph>
  <paragraph num="B.">
    <text>A person may not begin physical construction of a new facility without having submitted a complete permit application and having received a final permit under this chapter.</text>
  </paragraph>
  <paragraph num="C.">
    <text>A facility that is no longer operating but is maintained to permanently contain CHS and does not receive any additional CHS shall also be required to obtain a valid permit from the Department.</text>
  </paragraph>
  <paragraph num="D.">
    <text>A permit may be issued or denied for one or more units at a facility without simultaneously issuing or denying a permit to all of the units at the facility.</text>
  </paragraph>
  <paragraph num="E.">
    <text>Record Keeping. Applicants shall keep records of all data used to complete permit applications and any supplemental information submitted under this chapter for a period of at least 3 years from the date the application is signed.</text>
  </paragraph>
</regulation>