#### Regulation .06 Issuance of Failing Certificate.

*COMAR 26.16.02.06*

A. If an inspection demonstrates that a unit has not been brought into compliance with the applicable standards under Environment Article, §6-804, 6-815, or 6-819, Annotated Code of Maryland, the unit is considered to have failed the inspection and a failing certificate shall be issued.

B. If a unit fails inspection, the lead paint inspection contractor shall submit a copy of the failing certificate to the Department within 30 calendar days following the inspection or receipt of the laboratory analysis of dust samples.