<regulation prefix="Regulation" num=".08" citation="COMAR 26.17.01.08" title_num="26" subtitle_num="17" chapter_num="01" heading="Approval or Denial of Erosion and Sediment Control Plans.">
  <paragraph num="A.">
    <text>Review of Plans.</text>
    <paragraph num="(1)">
      <text>The approval authority shall review and approve an erosion and sediment control plan in accordance with the criteria contained in the “2011 Maryland Standards and Specifications for Soil Erosion and Sediment Control.”</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The approval authority shall assess the adequacy of the proposed erosion and sediment control measures to minimize erosion and keep sediment on site.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>When appropriate, an on-site evaluation shall be conducted as part of the review process in order to provide proper consideration of existing conditions and proposed control measures.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>The approval authority reserves the right to deny approval or impose conditions necessary to prevent:</text>
    <paragraph num="(1)">
      <text>A nuisance or dangerous condition;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Sediment pollution; or</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Adverse impacts to public safety and welfare.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>The approval authority may withhold approval when it determines that:</text>
    <paragraph num="(1)">
      <text>An owner/developer has not complied with the provisions of an outstanding order; or</text>
    </paragraph>
    <paragraph num="(2)">
      <text>There is a violation of the terms of an existing:</text>
      <paragraph num="(a)">
        <text>Grading permit;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Building permit; or</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Erosion and sediment control plan or related approval, permit, or license.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>In jurisdictions that are not delegated, the approval authority shall forward one copy of each approved plan to the Administration upon plan approval.</text>
  </paragraph>
  <paragraph num="E.">
    <text>For plans approved by the Administration:</text>
    <paragraph num="(1)">
      <text>Approved plans will be stamped approved;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The Administration shall send a letter of approval to the owner/developer; and</text>
    </paragraph>
    <paragraph num="(3)">
      <text>A copy of the approved plan will be kept by the Administration.</text>
    </paragraph>
  </paragraph>
  <paragraph num="F.">
    <text>Expiration of Approved Erosion and Sediment Control Plans.</text>
    <paragraph num="(1)">
      <text>Approved erosion and sediment control plans remain valid for 3 years from the date of approval, except surface mines and landfill plans, which remain valid for 5 years from the date of approval.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Erosion and sediment control plan approvals may be extended or renewed by the approval authority.</text>
    </paragraph>
  </paragraph>
  <paragraph num="G.">
    <text>Grandfathering of approved plans.</text>
    <paragraph num="(1)">
      <text>This chapter applies to all projects that do not have final approval for erosion and sediment control plans by January 9, 2013.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>A plan that has received final approval by January 9, 2013 may be reapproved under its existing conditions if grading activities have begun on the site by January 9, 2015, with the exception of stabilization requirements.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Stabilization practices on all projects must be in compliance with the requirements of this chapter by January 9, 2013, regardless of when an erosion and sediment control plan was approved.</text>
    </paragraph>
  </paragraph>
</regulation>