<chapter num="02" heading="Stormwater Management" title_num="26" subtitle_num="17">
  <regulation prefix="Regulation" num=".01" heading="Purpose and Scope.">
    <paragraph num="A.">
      <text>The primary goals of the State and local stormwater management programs are to maintain after development, as nearly as possible, the predevelopment runoff characteristics, and to reduce stream channel erosion, pollution, siltation and sedimentation, and local flooding by implementing environmental site design to the maximum extent practicable and using appropriate structural best management practices only when necessary.</text>
    </paragraph>
    <paragraph num="B.">
      <text>These regulations for stormwater management apply to the development or redevelopment of land for residential, commercial, industrial, or institutional use, but do not apply to agricultural land management practices. This chapter specifies the minimum content of county and municipal ordinances, responsibilities of the Administration regarding the review of the county and municipal stormwater management programs, and approval of State-constructed projects for stormwater management by the Department of the Environment.</text>
    </paragraph>
    <paragraph num="C.">
      <text>This chapter applies to all new development and redevelopment projects that do not have final approval for erosion and sediment control and stormwater management plans by May 4, 2010.</text>
    </paragraph>
    <paragraph num="D.">
      <text>The provisions of these regulations may not be construed to affect the requirements for a project located in an Intensely Developed Area of the Chesapeake and Atlantic Coastal Bays Critical Area to comply with the 10 percent Pollution Reduction Requirement under COMAR 27.01.02.03D(3).</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".01-1" heading="Incorporation by Reference.">
    <paragraph num="A.">
      <text>In this chapter, the following documents are incorporated by reference.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Documents Incorporated.</text>
      <paragraph num="(1)">
        <text>The 2000 Maryland Stormwater Design Manual, Volumes I &amp; II (Maryland Department of the Environment, April 2000), Supplement 1, is incorporated by reference by the Administration and shall serve as the official guide for stormwater management principles, methods, and practices.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>USDA Natural Resources Conservation Service Maryland Conservation Practice Standard Pond Code 378 (January 2000).</text>
      </paragraph>
      <paragraph num="(3)">
        <text>40 CFR §122.26(b)(14)(i)—(xi).</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".01-2" heading="Grandfather Provisions.">
    <paragraph num="A.">
      <text>In this regulation, the following terms have the meanings indicated:</text>
      <paragraph num="(1)">
        <text>Administrative Waiver.</text>
        <paragraph num="(a)">
          <text>“Administrative waiver” means a decision by the approving agency pursuant to this regulation to allow the construction of a development to be governed by the stormwater management ordinance in effect as of May 4, 2009, in the local jurisdiction where the project will be located.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Administrative waiver” is distinct from a waiver granted pursuant to Regulation .05C of this chapter.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Approval.</text>
        <paragraph num="(a)">
          <text>“Approval” means a documented action by a county or municipality following a review to determine and acknowledge the sufficiency of submitted material to meet the requirements of a specified stage in a local development review process.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Approval” does not mean an acknowledgement by the approving agency that submitted material has been received for review.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Final Project Approval.</text>
        <paragraph num="(a)">
          <text>“Final project approval” means approval of the final stormwater management plan and erosion and sediment control plan required to construct a project's stormwater management facilities.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Final project approval” includes securing bonding or financing for final development plans if either is required as a prerequisite for approval.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>“Preliminary project approval” means an approval as part of a local preliminary development or planning review process that includes, at a minimum:</text>
        <paragraph num="(a)">
          <text>The number of planned dwelling units or lots;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The proposed project density;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The proposed size and location of all land uses for the project;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>A plan that identifies:</text>
          <paragraph num="(i)">
            <text>The proposed drainage patterns;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The location of all points of discharge from the site; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The type, location, and size of all stormwater management measures based on site-specific stormwater management requirement computations; and</text>
          </paragraph>
        </paragraph>
        <paragraph num="(e)">
          <text>Any other information required by the approving agency including, but not limited to:</text>
          <paragraph num="(i)">
            <text>The proposed alignment, location, and construction type and standard for all roads, access ways, and areas of vehicular traffic;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>A demonstration that the methods by which the development will be supplied with water and wastewater service are adequate; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The size, type, and general location of all proposed wastewater and water system infrastructure.</text>
          </paragraph>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>An approving agency may grant an administrative waiver to a development that received a preliminary project approval prior to May 4, 2010.  Administrative waivers expire according to §C of this regulation and may be extended according to §D of this regulation.</text>
    </paragraph>
    <paragraph num="C.">
      <text>Expiration of Administrative Waivers.</text>
      <paragraph num="(1)">
        <text>Except as provided for in §D of this regulation, an administrative waiver shall expire on:</text>
        <paragraph num="(a)">
          <text>May 4, 2013, if the development does not receive final project approval prior to that date; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>May 4, 2017, if the development receives final project approval prior to May 4, 2013.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>All construction authorized pursuant to an administrative waiver must be completed by May 4, 2017, or, if the waiver is extended as provided in §D of this regulation, by the expiration date of the waiver extension.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Extension of Administrative Waivers.</text>
      <paragraph num="(1)">
        <text>Except as provided in §D(2) of this regulation, an administrative waiver shall not be extended.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>An administrative waiver may only be extended if, by May 4, 2010, the development:</text>
        <paragraph num="(a)">
          <text>Has received a preliminary project approval; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Was subject to a Development Rights and Responsibilities Agreement, a Tax Increment Financing approval, or an Annexation Agreement.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Administrative waivers extended according to §D(2) of this regulation shall expire when the Development Rights and Responsibilities Agreement, the Tax Increment Financing approval, or the Annexation Agreement expires.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Definitions.">
    <paragraph num="A.">
      <text>The following definitions describe the meaning of terms used in this chapter and the 2000 Maryland Stormwater Design Manual, Volumes I &amp; II. The definitions will be valid unless the context in which they are used clearly requires a different meaning. Terms not defined below shall have the meanings given to them in the relevant statutes or, if not defined in statutes, the meanings attributed by common use. The definitions for these terms are provided below as a convenience, but persons affected by the Department's regulations should be aware that these definitions are subject to amendment by the General Assembly.</text>
    </paragraph>
    <paragraph num="B.">
      <text>In this chapter, the following terms have the meanings indicated.</text>
      <paragraph num="(1)">
        <text>“Administration” means the Water Management Administration.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>“Agricultural land management practices” means those methods and procedures used in the cultivation of land in order to further crop and livestock production and conservation of related soil and water resources.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>“Approving agency” means the entity responsible for review and approval of stormwater management plans.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>“Aquifer” means a porous water-bearing geologic formation generally restricted to materials capable of yielding an appreciable supply of water.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>“Best management practice (BMP)” means a structural device or nonstructural practice designed to temporarily store or treat stormwater runoff in order to mitigate flooding, reduce pollution, and provide other amenities.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>“Channel protection storage volume” means the volume used to design structural management practices to control stream channel erosion. Methods for calculating the channel protection storage volume are specified in the 2000 Maryland Stormwater Design Manual, Volumes I &amp; II.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>“Concept plan” means the first of three required plan approvals that includes the information necessary to allow an initial evaluation of a proposed project.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>“Department” means the Department of the Environment.</text>
      </paragraph>
      <paragraph num="(9)">
        <text>“Design Manual” means the 2000 Maryland Stormwater Design Manual, Volumes I &amp; II, that serves as the official guide for stormwater management principles, methods, and practices.</text>
      </paragraph>
      <paragraph num="(10)">
        <text>“Detention structure” means a permanent structure for the temporary storage of runoff which is designed so as not to create a permanent pool of water.</text>
      </paragraph>
      <paragraph num="(11)">
        <text>“Develop land” means to change the runoff characteristics of a parcel of land in conjunction with residential, commercial, industrial, or institutional construction or alteration.</text>
      </paragraph>
      <paragraph num="(12)">
        <text>“Direct discharge” means the concentrated release of stormwater to tidal waters or vegetated tidal wetlands from new development or redevelopment projects in the Critical Area.</text>
      </paragraph>
      <paragraph num="(13)">
        <text>“Direct runoff” means the flow of rainwater, snowmelt, or spring flow over the land surface toward stream channels.</text>
      </paragraph>
      <paragraph num="(14)">
        <text>“Drainage area” means that area contributing runoff to a single point measured in a horizontal plane, which is enclosed by a ridge line.</text>
      </paragraph>
      <paragraph num="(15)">
        <text>Environmental Site Design.</text>
        <paragraph num="(a)">
          <text>“Environmental site design (ESD)” means using small-scale stormwater management practices, nonstructural techniques, and better site planning to mimic natural hydrologic runoff characteristics and minimize the impact of land development on water resources.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Environmental site design (ESD)” design methods are specified in the Design Manual.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(16)">
        <text>“Extended detention” means a stormwater design feature that provides gradual release of a volume of water in order to increase settling of pollutants and protect downstream channels from frequent storm events. Methods for designing extended detention BMPs are specified in the Design Manual.</text>
      </paragraph>
      <paragraph num="(17)">
        <text>“Extreme flood volume” means the storage volume required to control those infrequent but large storm events in which overbank flows reach or exceed the boundaries of the 100-year floodplain.</text>
      </paragraph>
      <paragraph num="(18)">
        <text>“Final stormwater management plan” means the last of three required plan approvals that includes the information necessary to allow all approvals and permits to be issued by the appropriate authority.</text>
      </paragraph>
      <paragraph num="(19)">
        <text>“Flow attenuation” means prolonging the flow time of runoff to reduce the peak discharge.</text>
      </paragraph>
      <paragraph num="(20)">
        <text>“Impervious area” means any surface that does not allow stormwater to infiltrate into the ground.</text>
      </paragraph>
      <paragraph num="(21)">
        <text>“Infiltration” means the passage or movement of water into the soil surface.</text>
      </paragraph>
      <paragraph num="(22)">
        <text>“Maximum extent practicable (MEP)” means designing stormwater management systems so that all reasonable opportunities for using ESD planning techniques and treatment practices are exhausted and, only where absolutely necessary, a structural BMP is implemented.</text>
      </paragraph>
      <paragraph num="(23)">
        <text>“Off-site stormwater management” means the design and construction of a facility necessary to control stormwater from more than one development.</text>
      </paragraph>
      <paragraph num="(24)">
        <text>“On-site stormwater management” means the design and construction of systems necessary to control stormwater within an immediate development.</text>
      </paragraph>
      <paragraph num="(25)">
        <text>“Overbank flood protection volume” means the volume controlled by structural practices to prevent an increase in the frequency of out-of-bank flooding generated by development. Methods for calculating the overbank flood protection volume are specified in the Design Manual.</text>
      </paragraph>
      <paragraph num="(26)">
        <text>“Person” means the federal government, the State, any county, municipal corporation, or other political subdivision of the State, or any of their units, or an individual, receiver, trustee, guardian, executor, administrator, fiduciary, or representative of any kind, or any partnership, firm, association, public or private corporation, or any other entity.</text>
      </paragraph>
      <paragraph num="(27)">
        <text>“Planning techniques” means a combination of strategies employed early in project design to reduce impact from development and to incorporate natural features into a stormwater management plan.</text>
      </paragraph>
      <paragraph num="(28)">
        <text>“Recharge volume” means that portion of the water quality volume used to maintain ground water recharge rates at development sites. Methods for calculating the recharge volume are specified in the Design Manual.</text>
      </paragraph>
      <paragraph num="(29)">
        <text>“Redevelopment” means any construction, alteration, or improvement performed on sites where existing land use is commercial, industrial, institutional, or multifamily residential and the existing site impervious area exceeds 40 percent.</text>
      </paragraph>
      <paragraph num="(30)">
        <text>“Retention structure” means a permanent structure that provides for the storage of runoff by means of a permanent pool of water.</text>
      </paragraph>
      <paragraph num="(31)">
        <text>“Retrofitting” means the construction of a structural BMP in a previously developed area, the modification of an existing structural BMP, or the implementation of a nonstructural practice to improve water quality over current conditions.</text>
      </paragraph>
      <paragraph num="(32)">
        <text>“Sediment” means soils or other surficial materials transported or deposited by the action of wind, water, ice, or gravity as a product of erosion.</text>
      </paragraph>
      <paragraph num="(33)">
        <text>“Site” means any tract, lot, parcel of land, or combination of tracts, lots, parcels of land that are in one ownership, or are contiguous and in diverse ownership where development is to be performed as part of a unit, subdivision, or project.</text>
      </paragraph>
      <paragraph num="(34)">
        <text>“Site development plan” means the second of three required plan approvals that includes the information necessary to allow a detailed evaluation of a proposed project.</text>
      </paragraph>
      <paragraph num="(35)">
        <text>“Stormwater” means water that originates from a precipitation event.</text>
      </paragraph>
      <paragraph num="(36)">
        <text>“Stormwater management” means, for:</text>
        <paragraph num="(a)">
          <text>Quantitative control, a system of vegetative and structural measures that control the increased volume and rate of surface runoff caused by man-made changes to the land; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Qualitative control, a system of vegetative, structural, and other measures that reduce or eliminate pollutants that might otherwise be carried by surface runoff.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(37)">
        <text>“Stormwater Management Subtitle” means Environment Article, Title 4, Subtitle 2, Annotated Code of Maryland and cumulative supplement.</text>
      </paragraph>
      <paragraph num="(38)">
        <text>“Stormwater management system” means natural areas, ESD practices, stormwater management measures, and any other structure through which stormwater flows, infiltrates, or discharges from a site.</text>
      </paragraph>
      <paragraph num="(39)">
        <text>“Water quality volume” means the volume needed to capture and treat 90 percent of the average annual runoff volume at a development site. Methods for calculating the water quality volume are specified in the Design Manual.</text>
      </paragraph>
      <paragraph num="(40)">
        <text>“Watershed” means the total drainage area contributing runoff to a single point.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="General Provisions.">
    <paragraph num="A.">
      <text>The Administration is responsible for implementing and supervising the stormwater management program which is established by the Stormwater Management Subtitle. This responsibility shall include, but is not limited to:</text>
      <paragraph num="(1)">
        <text>Establishing policies, procedures, standards, model ordinances, and criteria relating to stormwater management;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Reviewing and approving:</text>
        <paragraph num="(a)">
          <text>County stormwater management ordinances,</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Municipal stormwater management ordinances,</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Stormwater management program implementation and operation, and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Stormwater management plans for State and federal construction projects which shall be subject to the requirements of this chapter;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Inspecting and enforcing stormwater management on all State and federal construction projects which shall be subject to the requirements of this chapter;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Inspection and enforcement in conjunction with local governmental authorities;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Developing guidelines and regulations;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Assisting local jurisdictions with improving and maintaining their technical capabilities regarding:</text>
        <paragraph num="(a)">
          <text>Hydrologic and hydraulic analyses,</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Utilization of State adopted standards and specifications for stormwater management, and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Stormwater management plan review;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(7)">
        <text>Training assistance to local jurisdictions for construction and maintenance inspections of stormwater management systems;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Developing public educational programs; and</text>
      </paragraph>
      <paragraph num="(9)">
        <text>Evaluating the effectiveness of stormwater control measures in eliminating adverse stream quality impacts.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Matters of policy, procedures, standards, criteria, approvals, inspection, and enforcement relating to the Stormwater Management Subtitle shall be established by the Administration subject to the jurisdiction of the Secretary of the Environment. The stormwater management programs which are adopted by the counties and municipalities shall include stormwater management criteria consistent with the standards, procedures, and regulations of the Administration. A variation of requirements by a county or municipality on a specific watershed may not be valid unless approved by the Administration. All State and federal development in the watershed shall be reviewed subject to the same variations and requirements by the Administration.</text>
    </paragraph>
    <paragraph num="C.">
      <text>Inspection and Review.</text>
      <paragraph num="(1)">
        <text>Initially, and at least once every 3 years after that, the Administration shall inspect and review the stormwater management programs of the counties and municipalities and evaluate the effectiveness of the programs.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>To be found acceptable, a stormwater management program shall have:</text>
        <paragraph num="(a)">
          <text>An Administration-approved stormwater management ordinance in effect;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Stormwater management planning and approval processes that provide:</text>
          <paragraph num="(i)">
            <text>Stormwater management for every land development subject to this chapter;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The implementation of ESD to the MEP; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The ability and the information necessary to review adequately proposed installation and maintenance measures for stormwater management;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>Inspection and enforcement procedures that ensure the proper construction and maintenance of approved stormwater management measures.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Upon completion of its review and evaluation, the Administration shall submit the findings within 30 days to the appropriate governing authority. The Administration shall also publish the results of the periodic reviews in one document and conduct a public informational meeting concerning the reviews.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>If a county or municipality is found not to have an acceptable stormwater management program, the Department may:</text>
      <paragraph num="(1)">
        <text>Issue an order requiring that necessary corrective action be taken within a reasonably prescribed time; or</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Impose other sanctions as authorized by law.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>In order to assure that Administration-approved programs reflect the policies established in the Design Manual, each county or municipality shall submit proposed revisions to its ordinance to the Administration by November 11, 2009. Each county and municipality shall adopt a revised ordinance by May 4, 2010, in order to require that all new development and redevelopment projects implement the policies and practices established in the Design Manual. Descriptions of other program elements shall be submitted as requested by the Administration.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="Stormwater Management Ordinances.">
    <paragraph num="A.">
      <text>Each county and municipality shall adopt ordinances necessary to implement a stormwater management program. Subsequently, counties and municipalities shall submit any proposed amendments to the Administration for review and approval. By joint action with the county, a municipality may adopt the stormwater management ordinance of its respective county.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Each local ordinance shall provide for:</text>
      <paragraph num="(1)">
        <text>A comprehensive stormwater management plan review and approval process that:</text>
        <paragraph num="(a)">
          <text>Considers all aspects of project planning, design, and construction from initial conception through final approval;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Requires the submission, review, and approval of interim plans at an increasing level of detail for specific stages of project development;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Provides for coordinated input for all plans from all appropriate agencies including, but not limited to, soil conservation districts and departments of planning, zoning, public works, and environmental protection; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Requires implementation of ESD to the MEP;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Exemptions and waivers;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Criteria and procedures for stormwater management;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Proper implementation of stormwater management in accordance with the approved plan;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Maintenance responsibilities and requirements including periodic inspection; and</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Penalties for noncompliance with the ordinances including suspension of construction activities when appropriate.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".05" heading="When Stormwater Management is Required.">
    <paragraph num="A.">
      <text>Unless the particular activity is exempted by this regulation, a person may not develop any land without an approved final stormwater management plan from the approving agency. A grading or building permit may not be issued for a property unless a final stormwater management plan has been approved that is consistent with:</text>
      <paragraph num="(1)">
        <text>The Stormwater Management Subtitle;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>This chapter;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The county or municipal ordinance.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The Design Manual for new development; and</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Policies established by the local approving agency for redevelopment.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>The following activities are exempt from the provisions of this chapter:</text>
      <paragraph num="(1)">
        <text>Additions or modifications to existing single family detached residential structures if they comply with §B(2) of this regulation;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Any developments that do not disturb over 5,000 square feet of land area; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Land development activities which the Administration determines will be regulated under specific State laws which provide for managing stormwater runoff.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Waivers.</text>
      <paragraph num="(1)">
        <text>County and municipal ordinances may contain waiver policies for individual developments if the ordinances are approved by the Administration. The Administration will approve county and municipal ordinances and waiver policies if:</text>
        <paragraph num="(a)">
          <text>They reasonably ensure that a development will not adversely impact stream quality;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Waiver decisions are made on a case-by-case basis; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The cumulative effects of the waiver policy are evaluated.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Except as provided in §C(3) and (5) of this regulation, stormwater management quantitative control waivers shall be granted only to those projects within areas where watershed management plans have been developed consistent with §E of this regulation.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Except as provided in §C(5) of this regulation, if watershed management plans consistent with §E of this regulation have not been developed, stormwater management quantitative control waivers may be granted to projects:</text>
        <paragraph num="(a)">
          <text>That have direct discharges to tidally influenced receiving waters;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>That are in-fill development located in a Priority Funding Area where the economic feasibility of the project is tied to the planned density, and where implementation of the 2009 regulatory requirements would result in a loss of the planned development density provided that:</text>
          <paragraph num="(i)">
            <text>Public water and sewer and stormwater conveyance exist;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The quantitative waiver is applied to the project for the impervious cover that previously existed on the site only;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>ESD to the MEP is used to meet the full water quality treatment requirements for the entire development; and</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>ESD to the MEP is used to provide full quantity control for all new impervious surfaces; or</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>When the approving agency determines that circumstances exist that prevent the reasonable implementation of quantity control practices.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Except as provided in §C(5) of this regulation, stormwater management qualitative control waivers apply only to:</text>
        <paragraph num="(a)">
          <text>In-fill development projects where stormwater management implementation is not feasible;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Redevelopment projects if the requirements of §D of this regulation are satisfied; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Sites where the approving agency determines that circumstances exist that prevent the reasonable implementation of quality control practices.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>Stormwater management quantitative and qualitative control waivers may be granted for phased development projects if a system designed to meet the 2000 regulatory requirements and local ordinances for multiple phases has been constructed by May 4, 2010.  If the 2009 regulatory requirements cannot be met for future phases constructed after May 4, 2010, all reasonable efforts to incorporate ESD in future phases must be demonstrated.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Redevelopment.</text>
      <paragraph num="(1)">
        <text>An approving agency shall require that stormwater management be addressed for redevelopment. Unless otherwise specified by watershed management plans developed according to §E of this regulation, all redevelopment project designs shall do one of the following:</text>
        <paragraph num="(a)">
          <text>Reduce existing impervious area within the limit of disturbance by at least 50 percent according to the Design Manual;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Implement ESD to the MEP to provide water quality treatment for at least 50 percent of the existing impervious area within the limit of disturbance; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Use a combination of both §D(1)(a) and (b) of this regulation for at least 50 percent of the existing site impervious area.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Alternative stormwater management measures may be used to meet the requirements in §D(1) of this regulation if the developer satisfactorily demonstrates to the approving agency that impervious area reduction and ESD have been implemented to the MEP. Alternative stormwater management measures include, but are not limited to:</text>
        <paragraph num="(a)">
          <text>An on-site structural BMP;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>An off-site structural BMP to provide water quality treatment for an area equal to or greater than 50 percent of the existing impervious area; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A combination of impervious area reduction, ESD implementation, and an on-site or off-site structural BMP for an area equal to or greater than 50 percent of the existing site impervious area within the limit of disturbance.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>An approving agency may develop separate policies for providing water quality treatment for redevelopment projects if the requirements of §D(1) and (2) of this regulation cannot be met. Any separate redevelopment policy shall be reviewed and approved by the Administration and may include, but not be limited to:</text>
        <paragraph num="(a)">
          <text>A combination of ESD and an on-site or off-site structural BMP;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Retrofitting including existing BMP upgrades, filtering practices, and off-site ESD implementation;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Participation in a stream restoration project;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Pollution trading with another entity;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Design criteria based on watershed management plans developed according to §E of this regulation;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Payment of a fee-in-lieu; or</text>
        </paragraph>
        <paragraph num="(g)">
          <text>A partial waiver of the treatment requirements if ESD is not practicable.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>The determination of what alternative stormwater management measures will be available may be made by the approving agency at the appropriate point in the development review process.  Counties and municipalities shall consider the prioritization of alternative measures in §D(3) of this regulation after it has been determined that it is not practicable to meet the 2009 regulatory requirements using ESD.  In deciding what alternative measures may be required, an approving agency may consider factors including, but not limited to:</text>
        <paragraph num="(a)">
          <text>Whether the project is in an area targeted for development incentives such as a Priority Funding Area, a designated Transit Oriented Development area, or a designated Base Realignment and Closure Revitalization and Incentive Zone;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Whether the project is necessary to accommodate growth consistent with comprehensive plans; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Whether bonding and financing have already been secured based on an approved development plan.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>Stormwater management shall be addressed according to the new development requirements in the Design Manual for any net increase in impervious area.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>The recharge, channel protection storage volume, and overbank flood protection volume requirements specified in the Design Manual do not apply to redevelopment projects unless specified by the approving agency.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>On-site or off-site channel protection storage volume requirements as specified in the Design Manual may be imposed if watershed management plans developed according to §E of this regulation indicate that downstream flooding or erosion need to be addressed.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Variations of this redevelopment policy shall be approved by the Administration.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>An approving agency may develop quantitative waiver and redevelopment provisions for stormwater management that differ from the requirements of this chapter. These provisions shall be developed only as part of an overall watershed management plan. Watershed management plans developed for the purposes of implementing different stormwater management policies for waivers and redevelopment shall:</text>
      <paragraph num="(1)">
        <text>Include detailed hydrologic and hydraulic analyses to determine hydrograph timing;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Evaluate both quantity and quality management;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Include cumulative impact assessment of watershed development;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Identify existing flooding and receiving stream channel conditions;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Be conducted at a scale determined by the approving agency; and</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Specify where on-site or off-site quantitative and qualitative stormwater management practices are to be implemented.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".06" heading="Minimum Control Requirements.">
    <paragraph num="A.">
      <text>County and Municipal Requirements.</text>
      <paragraph num="(1)">
        <text>The minimum control requirements established in this section and the Design Manual shall be contained in each county and municipal ordinance as they apply to the applicable parts of the State. The minimum control requirements for each county and municipality are provided in §A(2) and (3) of this regulation.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>All counties and their incorporated municipalities shall require that the planning techniques, nonstructural and structural practices, and design methods specified in the Design Manual be used to implement ESD to the MEP. Stormwater management plans for development projects subject to this chapter shall be designed using the ESD sizing criteria, recharge volume, water quality volume, and channel protection storage volume criteria according to the Design Manual. The MEP standard is met when channel stability and 100 percent of the average annual predevelopment groundwater recharge are maintained, nonpoint source pollution is minimized, and structural stormwater management practices are used only if determined to be absolutely necessary.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Control of the 2-year frequency storm event, 10-year frequency storm event, or both is required according to the Design Manual if any county or municipality determines that additional stormwater management is necessary because historical flooding problems exist and downstream floodplain development and conveyance system design cannot be controlled.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>An approving agency may require more than the minimum control requirements specified in this regulation if hydrologic or topographic conditions warrant or if flooding, stream channel erosion, or water quality problems exist downstream from a proposed project.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Alternate minimum control requirements may be adopted subject to Administration approval. The Administration shall require a demonstration that alternative requirements will implement ESD to the MEP and control flood damages, accelerated stream erosion, water quality, and sedimentation, including, if necessary, address comprehensive watershed studies.</text>
    </paragraph>
    <paragraph num="C.">
      <text>Development in watersheds designated as interjurisdictional flood hazard watersheds within this chapter may not increase the downstream peak discharge for the 100-year frequency storm event and shall comply with flood management plans as approved by the Department in accordance with the Flood Hazard Management Act of 1976 (Environment Article, Title 5, Subtitle 8, Annotated Code of Maryland).</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".07" heading="Interjurisdictional Flood Hazard Watersheds.">
    <paragraph num="A.">
      <text>The watersheds specified in this regulation are interjurisdictional in nature and have documented flood damages to residential, commercial, industrial, or institutional structures. Development in the interjurisdictional flood hazard watershed may not increase the downstream peak discharge for the 100-year frequency storm event. Additionally, development shall comply with flood management plans as approved by the Department in accordance with the Flood Hazard Management Act of 1976 (Environment Article, Title 5, Subtitle 8, Annotated Code of Maryland). The following watersheds and all their tributaries are designated as interjurisdictional flood hazard watersheds:</text>
      <paragraph num="(1)">
        <text>Carroll Creek in Frederick City and Frederick County;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Gwynns Falls in Baltimore City and Baltimore County; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Jones Falls in Baltimore City and Baltimore County.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>The Administration shall periodically review watersheds to be included as interjurisdictional flood hazard watersheds for the purposes of this chapter. Any additional interjurisdictional watershed to be designated will be considered with respect to the:</text>
      <paragraph num="(1)">
        <text>Economic losses due to flood damages;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Expected upstream development;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Frequency of flooding;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Number and value of structures flooded; and</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Threat to life.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".08" heading="Stormwater Management Measures.">
    <paragraph num="A.">
      <text>The ESD planning techniques and practices and structural stormwater management measures established in this regulation and the Design Manual shall be contained in all county and municipal ordinances. Each ordinance shall require that a developer demonstrate that ESD has been implemented to the MEP and, only where absolutely necessary, is a structural BMP used in developing a stormwater management plan.</text>
    </paragraph>
    <paragraph num="B.">
      <text>ESD Planning Techniques and Practices.</text>
      <paragraph num="(1)">
        <text>The following planning techniques shall be applied according to the Design Manual to satisfy the minimum control requirements established in Regulation .06 of this chapter:</text>
        <paragraph num="(a)">
          <text>Preserving and protecting natural resources;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Conserving natural drainage patterns;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Minimizing impervious area;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Reducing runoff volume;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Using ESD practices to maintain 100 percent of the average annual predevelopment groundwater recharge volume for the site;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Using green roofs, permeable pavement, reinforced turf, and other alternative surfaces;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Limiting soil disturbance, mass grading, and compaction;</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Clustering development; and</text>
        </paragraph>
        <paragraph num="(i)">
          <text>Any practices approved by the Administration.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The following ESD treatment practices shall be designed according to the Design Manual to satisfy the minimum control requirements established in Regulation .06 of this chapter:</text>
        <paragraph num="(a)">
          <text>Disconnection of rooftop runoff;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Disconnection of nonrooftop runoff;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Sheetflow to conservation areas;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Rainwater harvesting;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Submerged gravel wetlands;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Landscape infiltration;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Infiltration berms;</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Dry wells;</text>
        </paragraph>
        <paragraph num="(i)">
          <text>Micro-bioretention;</text>
        </paragraph>
        <paragraph num="(j)">
          <text>Rain gardens;</text>
        </paragraph>
        <paragraph num="(k)">
          <text>Swales;</text>
        </paragraph>
        <paragraph num="(l)">
          <text>Enhanced filters; and</text>
        </paragraph>
        <paragraph num="(m)">
          <text>Any practices approved by the Administration.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The use of the ESD planning techniques and treatment practices specified in this section may not conflict with existing State law or local ordinances, regulations, or policies. Counties and municipalities shall modify planning and zoning ordinances and public works codes to eliminate any impediments to implementing ESD to the MEP according to the Design Manual.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Structural Stormwater Management Measures.</text>
      <paragraph num="(1)">
        <text>The following structural stormwater management practices shall be designed according to the Design Manual to satisfy the applicable minimum control requirements established in Regulation .06 of this chapter:</text>
        <paragraph num="(a)">
          <text>Stormwater management ponds;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Stormwater management wetlands;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Stormwater management infiltration;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Stormwater management filtering systems; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Stormwater management open channel systems.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The performance criteria specified in the Design Manual with regard to general feasibility, conveyance, pretreatment, treatment and geometry, environment and landscaping, and maintenance shall be considered when selecting structural stormwater management practices.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Structural stormwater management practices shall be selected to accommodate the unique hydrologic or geologic regions of the State.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Standard Plans.</text>
      <paragraph num="(1)">
        <text>Compliance with any of the following Standard Plans is considered to satisfy the minimum control requirements established in Regulation .06A(2) of this chapter.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Standard Plans. The following documents are incorporated by reference:</text>
        <paragraph num="(a)">
          <text>Standard Stormwater Management Plan for Agricultural Structures (SSDS — SP01);</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Standard Stormwater Management Plan for Poultry House Development on Maryland’s Eastern Shore (SSDS — SP02); and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Standard Stormwater Management Plan for Single Lot Residential Construction (SSDS — SP03).</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Compliance with an approved Soil Conservation and Water Quality Plan (SCWQP) is considered to satisfy the minimum control requirements established in Regulation .06A(2) of this chapter if the development:</text>
        <paragraph num="(a)">
          <text>Is an agricultural structure, or associated access roads and parking areas;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Complies with USDA Natural Resources Conservation Service Maryland Conservation Practice Standard Stormwater Runoff Control Code 570 (March 2013);</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Is not located within the Chesapeake and Atlantic Coastal Bays Critical Area; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Is not subject to the requirements of:</text>
          <paragraph num="(i)">
            <text>COMAR 26.08.04.09A;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>COMAR 26.08.04.09N; or</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>COMAR 26.17.04.05.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>An approving agency may require more than the minimum control measures. An approving agency may require that an engineered stormwater management plan be submitted if:</text>
        <paragraph num="(a)">
          <text>Otherwise required by statute or regulation;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The plan fails to meet ESD to the MEP;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Hydrologic or topographic conditions warrant; or</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Flooding, stream channel erosion, or water quality problems exist downstream from a proposed project.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>County and municipal ordinances shall specify that the ESD planning techniques and treatment practices and structural stormwater management measures used to satisfy the minimum control requirements in Regulation .06 of this chapter are documented and remain unaltered by subsequent property owners. Approval from the appropriate approving agency should be obtained before any stormwater management practice is altered.</text>
    </paragraph>
    <paragraph num="F.">
      <text>Alternative ESD planning techniques and treatment practices and structural stormwater management measures may be used for new development runoff control if they meet the performance criteria established in the Design Manual and are approved by the Administration. Practices used for redevelopment projects shall be approved by the appropriate approving agency.</text>
    </paragraph>
    <paragraph num="G.">
      <text>For purposes of modifying the minimum control requirements or design criteria, the owner/developer shall submit to the approving agency an analysis of the impacts of stormwater flows downstream in the watershed. The analysis shall include hydrologic and hydraulic calculations necessary to determine the impact of hydrograph timing modifications of the proposed development upon a dam, highway, structure, or natural point of restricted streamflow, established with the concurrence of the approving agency, downstream of the first downstream tributary whose drainage area equals or exceeds the contributing area to the project or stormwater management facility.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".09" heading="Stormwater Management Plans.">
    <paragraph num="A.">
      <text>The design of stormwater management plans shall be prepared by any individual whose qualifications are acceptable to the approving agency. The approving agency may require that the design be prepared by either a professional engineer, professional land surveyor, or landscape architect licensed in the State, as necessary to protect the public or the environment. If a stormwater BMP requires either a dam safety permit from the Department or small pond approval by the appropriate soil conservation district, the approving agency shall require that the design be prepared by a professional engineer licensed in the State.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Stormwater management and development plans shall be consistent with adopted and approved watershed management plans or flood management plans as approved by the Department in accordance with the Flood Hazard Management Act of 1976 (Environment Article, Title 5, Subtitle 8, Annotated Code of Maryland).</text>
    </paragraph>
    <paragraph num="C.">
      <text>An operation and maintenance plan shall be required as a condition of stormwater management plan approval.</text>
    </paragraph>
    <paragraph num="D.">
      <text>If a stormwater management plan involves direction of some or all runoff off of the site, it is the responsibility of the developer to obtain from adjacent property owners any easements or other necessary property interests concerning flowage of water. Approval of a stormwater management plan does not create or affect any right to direct runoff onto adjacent property without that property owner's permission.</text>
    </paragraph>
    <paragraph num="E.">
      <text>Contents and Submission of Stormwater Management Plans.</text>
      <paragraph num="(1)">
        <text>The owner/developer is responsible for submitting phased stormwater management plans for development projects according to the comprehensive review and approval process specified in Regulation .04 of this chapter, the Design Manual, and county and municipal stormwater management ordinances. Plans shall be submitted for the concept, site development, and final stormwater management construction phases of project design. Comments from the appropriate approval authority shall be addressed and approval received at each phase of project design before subsequent submissions.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The owner/developer shall submit a concept plan that provides sufficient information for an initial assessment of the proposed project and whether stormwater management can be provided according to this chapter and the Design Manual. Plans submitted for concept approval shall include, but are not limited to:</text>
        <paragraph num="(a)">
          <text>A map at a scale specified by the appropriate approval authority showing site location, existing natural features, water and other sensitive resources, topography, and natural drainage patterns;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The anticipated location of all proposed impervious areas, buildings, roadways, parking, sidewalks, utilities, and other site improvements;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The location of the proposed limit of disturbance, erodible soils, steep slopes, and areas to be protected during construction;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Preliminary estimates of stormwater management requirements, the selection and location of ESD practices to be used, and the location of all points of discharge from the site;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>A narrative that supports the concept design and describes how ESD will be implemented to the MEP; and</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Any other information required by the approving Agency.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Following concept plan approval by the appropriate authority, the owner or developer shall submit site development plans that reflect comments received during the previous review phase. Plans submitted for site development approval shall be of sufficient detail to allow site development to be reviewed and include but not be limited to:</text>
        <paragraph num="(a)">
          <text>All information provided during the concept plan review phase;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Final site layout, exact impervious area locations and acreages, proposed topography, delineated drainage areas at all points of discharge from the site, and stormwater volume computations for ESD practices and quantity control structures;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A proposed erosion and sediment control plan that contains the construction sequence, any phasing necessary to limit earth disturbances and impacts to natural resources, and an overlay plan showing the types and locations of ESD and erosion and sediment control practices to be used;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>A narrative that supports the site development design, describes how ESD will be used to meet the minimum control requirements, and justifies any proposed structural stormwater management measure; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Any other information required by the approving Agency.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Following site development approval by the appropriate authority, the owner/developer shall submit final erosion and sediment control and stormwater management plans that reflect the comments received during the previous review phase. Plans submitted for final approval shall be of sufficient detail to allow all approvals and permits to be issued according to the following:</text>
        <paragraph num="(a)">
          <text>Final erosion and sediment control plans shall be submitted according to COMAR 26.17.01.05; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Final stormwater management plans shall be submitted for approval in the form of construction drawings and be accompanied by a report that includes sufficient information to evaluate the effectiveness of the proposed runoff control design.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>Reports submitted for final stormwater management plan approval shall include, but are not limited to:</text>
        <paragraph num="(a)">
          <text>Geotechnical investigations including soil maps, borings, site-specific recommendations, and any additional information necessary for the final stormwater management design;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Drainage area maps depicting predevelopment and postdevelopment runoff flow path segmentation and land use;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Hydrologic computations of the applicable ESD and unified sizing criteria according to the Design Manual for all points of discharge from the site;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Hydraulic and structural computations for all ESD practices and structural stormwater management measures to be used;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>A narrative that supports the final stormwater management design; and</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Any other information required by the approving agency.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>Construction drawings submitted for final stormwater management plan approval shall include, but are not limited to:</text>
        <paragraph num="(a)">
          <text>A vicinity map;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Existing and proposed topography and proposed drainage areas, including areas necessary to determine downstream analysis for the proposed stormwater management facilities;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Any proposed improvements including the location of buildings or other structures, impervious surfaces, storm drainage facilities, and all grading;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The location of existing and proposed structures;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Any easements and rights-of-way;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The delineation, if applicable, of the 100-year floodplain and any on-site wetlands;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Structural and construction details including representative cross sections for all components of the proposed drainage system or systems and stormwater management facilities;</text>
        </paragraph>
        <paragraph num="(h)">
          <text>All necessary construction specifications;</text>
        </paragraph>
        <paragraph num="(i)">
          <text>A sequence of construction;</text>
        </paragraph>
        <paragraph num="(j)">
          <text>Data for total site area, disturbed area, new impervious area, and total impervious area;</text>
        </paragraph>
        <paragraph num="(k)">
          <text>A table showing the ESD and unified sizing criteria volumes required in the Design Manual;</text>
        </paragraph>
        <paragraph num="(l)">
          <text>A table of materials to be used for stormwater management facility planting;</text>
        </paragraph>
        <paragraph num="(m)">
          <text>All soil boring logs and locations;</text>
        </paragraph>
        <paragraph num="(n)">
          <text>An inspection and maintenance schedule;</text>
        </paragraph>
        <paragraph num="(o)">
          <text>Certification by the owner/developer that all stormwater management construction will be done according to this plan;</text>
        </paragraph>
        <paragraph num="(p)">
          <text>An as-built certification signature block to be executed after project completion; and</text>
        </paragraph>
        <paragraph num="(q)">
          <text>Any other information required by the approving agency.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="F.">
      <text>Standard plans specified in Regulation .08D of this chapter are considered an acceptable stormwater management plan for satisfying the requirements of §E of this regulation.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".10" heading="Construction Inspection and Enforcement.">
    <paragraph num="A.">
      <text>Before Beginning Construction.</text>
      <paragraph num="(1)">
        <text>All county and municipal ordinances shall require:</text>
        <paragraph num="(a)">
          <text>Advance notification of the beginning of construction by the owner/developer;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Documented regular inspections during construction of stormwater management systems;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Certification by a professional engineer licensed in the State documenting that structural practices have been constructed according to approved plans; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Effective enforcement procedures to ensure compliance with approved stormwater management plans.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The owner/developer shall notify the appropriate approving agency at least 48 hours before beginning any work in conjunction with stormwater management system construction.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Inspections shall be conducted by county or municipal staff or certified by a professional engineer licensed in the State. The periodic inspections shall be documented and reports maintained by the county or municipality. Written reports shall be prepared for every inspection and include:</text>
        <paragraph num="(a)">
          <text>The date and location of the inspection;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Whether construction was in compliance with the approved stormwater management plan;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Any variations from the approved construction specifications; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Any violations that exist.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>The owner/developer and on-site personnel shall be notified in writing when violations are observed. Written notification shall describe the nature of the violation and the required corrective action.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Work may not proceed until the work previously completed is approved by the appropriate inspection authority.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Regular inspections shall be made and documented for each ESD planning technique and practice at the stages of construction specified in the Design Manual. At a minimum, all ESD and other nonstructural practices shall be inspected upon completion of final grading, the establishment of permanent stabilization, and before issuance of use and occupancy approval.</text>
    </paragraph>
    <paragraph num="C.">
      <text>At a minimum, regular inspections shall be made and documented at the following specified stages of construction:</text>
      <paragraph num="(1)">
        <text>For ponds:</text>
        <paragraph num="(a)">
          <text>Upon completion of excavation to sub-foundation and, when required, installation of structural supports or reinforcement for structures, including but not limited to:</text>
          <paragraph num="(i)">
            <text>Core trenches for structural embankments,</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Inlet and outlet structures, anti-seep collars or diaphragms, and watertight connectors on pipes, and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Trenches for enclosed storm drainage facilities;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>During placement of structural fill, concrete, and installation of piping and catch basins;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>During backfill of foundations and trenches;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>During embankment construction; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Upon completion of final grading and establishment of permanent stabilization;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Wetlands—at the stages specified for pond construction in §B(1) of this regulation, during and after wetland reservoir area planting, and during the second growing season to verify a vegetation survival rate of at least 50 percent;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>For infiltration trenches:</text>
        <paragraph num="(a)">
          <text>During excavation to subgrade;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>During placement and backfill of under drain systems and observation wells;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>During placement of geotextiles and all filter media;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>During construction of appurtenant conveyance systems such as diversion structures, pre-filters and filters, inlets, outlets, orifices, and flow distribution structures; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Upon completion of final grading and establishment of permanent stabilization;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>For infiltration basins—at the stages specified for pond construction in §B(1) of this regulation and during placement and backfill of under drain systems;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>For filtering systems:</text>
        <paragraph num="(a)">
          <text>During excavation to subgrade;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>During placement and backfill of under drain systems;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>During placement of geotextiles and all filter media;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>During construction of appurtenant conveyance systems such as flow diversion structures, pre-filters and filters, inlets, outlets, orifices, and flow distribution structures; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Upon completion of final grading and establishment of permanent stabilization; and</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>For open channel systems:</text>
        <paragraph num="(a)">
          <text>During excavation to subgrade;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>During placement and backfill of under drain systems for dry swales;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>During installation or diaphragms, check dams, or weirs; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Upon completion of final grading and establishment of permanent stabilization.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>The county or municipality responsible for inspection and enforcement of approved stormwater management plans may, for enforcement purposes, use any one or a combination of the following actions:</text>
      <paragraph num="(1)">
        <text>A notice of violation shall be issued specifying the need for the violation to be corrected if stormwater management plan noncompliance is identified;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A stop work order shall be issued for the site by the county or municipality if a violation persists;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Bonds or securities may be withheld or the case may be referred for legal action if reasonable efforts to correct the violation have not been undertaken; or</text>
      </paragraph>
      <paragraph num="(4)">
        <text>In addition to any other sanctions, a civil action or criminal prosecution may be brought against any person in violation of the Stormwater Management Subtitle or this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Any step in the enforcement process may be taken at any time, depending on the severity of the violation.</text>
    </paragraph>
    <paragraph num="F.">
      <text>Once construction is complete, as-built plan certification shall be submitted by either a professional engineer or professional land surveyor licensed in the State to ensure that ESD planning techniques, treatment practices, and structural stormwater management measures and conveyance systems comply with the specifications contained in approved plans. At a minimum, as-built certification shall include a set of drawings comparing the approved stormwater management plan with what was constructed. Other information shall be submitted as required by the approving agency.</text>
    </paragraph>
    <paragraph num="G.">
      <text>Each county or municipality shall submit notice of construction completion to the Administration on a form supplied by the Administration for each stormwater management practice within 45 days of construction completion. If BMPs requiring soil conservation district approval are constructed, notice of construction completion shall also be submitted to the appropriate soil conservation district.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".11" heading="Maintenance.">
    <paragraph num="A.">
      <text>Maintenance requirements established in this regulation shall be contained in all county and municipal ordinances and shall provide for inspection and maintenance. The owner shall perform or cause to be performed preventive maintenance of all completed ESD treatment practices and structural stormwater management measures to ensure proper functioning. The responsible agency of the county or municipality shall ensure preventive maintenance through inspection of all stormwater management systems. The inspection shall occur during the first year of operation and then at least once every 3 years after that.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Inspection reports shall be maintained by the county or municipality on all stormwater management systems and shall include the following:</text>
      <paragraph num="(1)">
        <text>The date of inspection;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Name of inspector;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The condition of:</text>
        <paragraph num="(a)">
          <text>Vegetation or filter media;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Fences or other safety devices;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Spillways, valves, or other control structures;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Embankments, slopes, and safety benches;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Reservoir or treatment areas;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Inlet and outlet channels or structures;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Underground drainage;</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Sediment and debris accumulation in storage and forebay areas;</text>
        </paragraph>
        <paragraph num="(i)">
          <text>Any nonstructural practices to the extent practicable; and</text>
        </paragraph>
        <paragraph num="(j)">
          <text>Any other item that could affect the proper function of the stormwater management system;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Description of needed maintenance.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>County and municipal ordinances shall provide procedures to ensure that deficiencies indicated by inspections are rectified. The procedures shall include the following:</text>
      <paragraph num="(1)">
        <text>Notification to the owner of deficiency including a time frame for repairs;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Subsequent inspection to ensure completion of repairs; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Effective enforcement procedures if repairs are not undertaken or are not done properly.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <annotations>
    <annotation type="Authority">Environment Article, §§4-201 and 4-203, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: July 18, 1983 (10:14 Md. R. 1260)</annotation>
    <annotation type="History" subtype="Administrative History">Regulations .03A, and .08A, C, and G amended effective June 4, 1984 (11:11 Md. R. 962)</annotation>
    <annotation type="History" subtype="Administrative History">Chapter recodified from COMAR 08.05.05 to COMAR 26.09.02</annotation>
    <annotation type="History" subtype="Administrative History">Chapter recodified from COMAR 26.09.02 to COMAR 26.17.02, June 1996</annotation>
    <annotation type="History" subtype="Administrative History">Chapter revised effective October 2, 2000 (27:19 Md. R. 1733)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01 amended effective May 4, 2009 (36:9 Md. R. 652)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01D adopted as an emergency provision effective April 7, 2010 (37:10 Md. R. 719); adopted permanently effective July 26, 2010 (37:15 Md. R. 1001)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01-1B amended effective May 4, 2009 (36:9 Md. R. 652)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01-2 adopted as an emergency provision effective April 7, 2010 (37:10 Md. R. 719); adopted permanently effective July 26, 2010 (37:15 Md. R. 1001)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02B amended effective May 4, 2009 (36:9 Md. R. 652)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .03 amended effective May 4, 2009 (36:9 Md. R. 652)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .04B amended effective May 4, 2009 (36:9 Md. R. 652)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .05 amended effective May 4, 2009 (36:9 Md. R. 652)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .05C, D amended as an emergency provision effective April 7, 2010 (37:10 Md. R. 719); amended permanently effective July 26, 2010 (37:15 Md. R. 1001)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .06A, B amended effective May 4, 2009 (36:9 Md. R. 652)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .08 amended effective May 4, 2009 (36:9 Md. R. 652); July 29, 2019 (46:15 Md. R. 656)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09E amended effective May 4, 2009 (36:9 Md. R. 652)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09F adopted effective July 29, 2019 (46:15 Md. R. 656)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .10 amended effective May 4, 2009 (36:9 Md. R. 652)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .11A, B amended effective May 4, 2009 (36:9 Md. R. 652)</annotation>
  </annotations>
</chapter>