<?xml version='1.0' encoding='utf-8'?>
<regulation prefix="Regulation" num=".02" citation="COMAR 26.20.07.02" title_num="26" subtitle_num="20" chapter_num="07" heading="Permit Revisions.">
  <paragraph num="A.">
    <text>A revision to a permit shall be obtained:</text>
    <paragraph num="(1)">
      <text>Before implementation of any changes in the surface coal mining or reclamation operations approved under the original permit, when these changes constitute a significant departure from the method of conduct of mining or reclamation operations contemplated by the original permit;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>In order to continue operation, after any material reduction of the performance bond or other equivalent guarantee upon which the original permit was issued; or</text>
    </paragraph>
    <paragraph num="(3)">
      <text>As otherwise required under the Regulatory Program.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Any application for revision which proposes significant alterations in the original permit shall be:</text>
    <paragraph num="(1)">
      <text>Subject to the applicable requirements of COMAR 26.20.02 and 26.20.03;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Approved or disapproved by the Bureau in accordance with COMAR 26.20.04 and 26.20.05; and</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Submitted to the Bureau at least 150 days before the permittee desires to revise the permitted operation.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>Any application for a revision which does not propose significant alterations in the original permit shall be:</text>
    <paragraph num="(1)">
      <text>Submitted to the Bureau at least 5 days before the permittee desires to revise the permitted operation;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Accompanied by such narratives, maps, cross sections, and documentation as would be required if the revision were part of a new permit application; and</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Approved or disapproved by the Bureau if it would have been approved or disapproved as part of a new permit application.</text>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>The following revisions are not considered significant alterations in the original permit:</text>
    <paragraph num="(1)">
      <text>Changes in the seam of coal to be mined, with the approval of the mineral owner;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Mining within 300 feet of an occupied dwelling, with the approval of the owner;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Increases in the open acre limit;</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Decreases in the open acre limit;</text>
    </paragraph>
    <paragraph num="(5)">
      <text>Decreases in the total permit acres;</text>
    </paragraph>
    <paragraph num="(6)">
      <text>Relocation of haul roads or culverts and turnouts;</text>
    </paragraph>
    <paragraph num="(7)">
      <text>Changes in the mining sequence or the direction or length of cuts;</text>
    </paragraph>
    <paragraph num="(8)">
      <text>Relocation of topsoil stockpiles;</text>
    </paragraph>
    <paragraph num="(9)">
      <text>Changes in the blasting plan, except that no changes are permitted to the hours of blasting without prior publication of the new schedule;</text>
    </paragraph>
    <paragraph num="(10)">
      <text>Changes in the placement of spoil material or handling of acid-producing or toxic-producing material;</text>
    </paragraph>
    <paragraph num="(11)">
      <text>Changes in the location or design of drainage control structures;</text>
    </paragraph>
    <paragraph num="(12)">
      <text>Changes in the location of water treatment facilities or method of water treatment;</text>
    </paragraph>
    <paragraph num="(13)">
      <text>Changes in the location, design, or number of diversion ditches;</text>
    </paragraph>
    <paragraph num="(14)">
      <text>Changes in the method or sequence of regrading;</text>
    </paragraph>
    <paragraph num="(15)">
      <text>Changes in the mining and reclamation equipment;</text>
    </paragraph>
    <paragraph num="(16)">
      <text>Changes in the method of procedure for redistributing topsoil material;</text>
    </paragraph>
    <paragraph num="(17)">
      <text>Changes in the seed bed preparation;</text>
    </paragraph>
    <paragraph num="(18)">
      <text>Change in the rate of application and analysis of lime and fertilizer;</text>
    </paragraph>
    <paragraph num="(19)">
      <text>Changes in the planting method, revegetation species or rate of application, and type or rate of application of mulch;</text>
    </paragraph>
    <paragraph num="(20)">
      <text>Changes in the seasonal maintenance plan for revegetated areas;</text>
    </paragraph>
    <paragraph num="(21)">
      <text>Incidental boundary revisions, provided the new permit area is contiguous to the original permit area and that no portion of the new area is more than 250 feet from the original area;</text>
    </paragraph>
    <paragraph num="(22)">
      <text>Increase in total approved permit acres of not more than 10 acres per permit over the life of the permit.</text>
    </paragraph>
  </paragraph>
</regulation>