<?xml version='1.0' encoding='utf-8'?>
<regulation prefix="Regulation" num=".06" citation="COMAR 26.20.21.06" title_num="26" subtitle_num="20" chapter_num="21" heading="Siltation Structures.">
  <paragraph num="A.">
    <text>Exemptions. Exemptions to the requirements of this regulation may be granted if the:</text>
    <paragraph num="(1)">
      <text>Disturbed drainage area within the total disturbed area is small; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Operator demonstrates that siltation structures and alternate sediment control measures are not necessary to meet the effluent limitations in this chapter and the applicable State and federal water quality standards for receiving waters.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>In this regulation, the following terms have the meanings indicated.</text>
  </paragraph>
  <paragraph num="C.">
    <text>Terms Defined.</text>
    <paragraph num="(1)">
      <text>Disturbed Area.</text>
      <paragraph num="(a)">
        <text>“Disturbed area” means an area from which vegetation, topsoil, or overburden is removed or land occupied by topsoil stockpiles, spoil piles, the open pit, access or haul roads, haulageways, storage areas, shop areas, processing and shipping areas, drainage or sediment control structures, coal processing wastes, underground development waste, or non-coal waste.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>“Disturbed area” does not include those areas where the:</text>
        <paragraph num="(i)">
          <text>Only surface mining activities include diversion ditches, siltation structures, or roads that are designed, constructed, and maintained in accordance with COMAR 26.20.19; and</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>Upstream area is not otherwise disturbed by the operator.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>“Other treatment facilities” means any chemical treatments, such as flocculation, or mechanical structures, such as clarifiers, that have a point source discharge and that are utilized to prevent additional contribution of suspended solids to streamflow or runoff outside the permit area.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>“Siltation structure” means a sedimentation pond, a series of sedimentation ponds, or other treatment facility.</text>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>General Requirements for Siltation Structures. All siltation structures:</text>
    <paragraph num="(1)">
      <text>Shall prevent additional contributions of suspended solids sediment to streamflow or runoff outside the permit area to the extent possible using the best technology currently available;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Shall collect all surface drainage from the disturbed area before leaving the permit area, except as provided in §A of this regulation;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Shall be constructed before beginning a surface mining activity in an area and, upon construction, be certified by a qualified professional engineer as being constructed in accordance with the approved design;</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Shall be designed, constructed, and maintained in accordance with Regulation .08 of this chapter if the structure impounds water;</text>
    </paragraph>
    <paragraph num="(5)">
      <text>Shall be maintained until:</text>
      <paragraph num="(a)">
        <text>Removal is authorized by the Department;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The disturbed area has been stabilized and revegetated;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>The quality of the untreated drainage from the disturbed area meets applicable State and federal water quality standards for the receiving stream; and</text>
      </paragraph>
    </paragraph>
    <paragraph num="(6)">
      <text>May not be removed if augmented seeding has occurred within the last 2 years.</text>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>When a siltation structure is removed, the land on which the structure was located shall be regraded and revegetated in accordance with the approved reclamation plan.</text>
  </paragraph>
  <paragraph num="F.">
    <text>The design, construction, and maintenance of a siltation structure does not relieve the person from compliance with applicable effluent limitations.</text>
  </paragraph>
  <paragraph num="G.">
    <text>Sedimentation Ponds. Sedimentation ponds shall be used individually or in series and shall be:</text>
    <paragraph num="(1)">
      <text>Designed, constructed, and maintained in accordance with Regulation .08 of this chapter;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Located as near as possible to the disturbed area and out of perennial streams, unless approved by the Bureau; and</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Designed, constructed, and maintained to:</text>
      <paragraph num="(a)">
        <text>Provide a minimum sediment storage volume of 67 cubic yards per acre of drainage area to the pond;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Provide adequate detention time to allow the effluent from the ponds to meet State and federal effluent limitations;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Contain or treat the 10-year, 24-hour precipitation event so there is no outflow through the emergency spillway unless a lesser design event is approved by the Bureau based on terrain, climate, other site conditions, and on a demonstration by the operator that the effluent limits of Regulation .02 of this chapter will be met;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Provide a nonclogging dewatering device adequate to maintain the detention time;</text>
      </paragraph>
      <paragraph num="(e)">
        <text>Minimize, to the extent possible, short circuiting; and</text>
      </paragraph>
      <paragraph num="(f)">
        <text>Provide for the removal of sediment when the volume of sediment accumulates to 60 percent of the sediment storage volume.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="H.">
    <text>The dewatering device required by §G(3)(d) of this regulation may not be located at an elevation lower than the maximum elevation of the sediment storage volume, unless approval is obtained from the Bureau.</text>
  </paragraph>
  <paragraph num="I.">
    <text>Other Treatment Facilities. Other treatment facilities shall be designed:</text>
    <paragraph num="(1)">
      <text>In accordance with the applicable requirements of this section; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>To contain or treat the 10-year, 24-hour precipitation event unless a lesser design event is approved by the Bureau in accordance with §G(3)(c) of this regulation.</text>
    </paragraph>
  </paragraph>
</regulation>