<?xml version='1.0' encoding='utf-8'?>
<subtitle num="22" heading="Coastal Facilities Review" title_num="26" title_heading="Department of the Environment">
  <chapter num="01" heading="Coastal Facilities Review">
    <regulation prefix="Regulation" num=".01" heading="Definitions.">
      <paragraph num="A.">
        <text>In this chapter, the following terms have the meanings indicated.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Terms Defined.</text>
        <paragraph num="(1)">
          <text>“Coastal area” means all that land and water lying within Anne Arundel, Baltimore, Calvert, Caroline, Cecil, Charles, Dorchester, Harford, Kent, Prince George's, Queen Anne's, St. Mary's, Somerset, Talbot, Wicomico, and Worcester counties, including the waters of the Chesapeake Bay, and waters lying seaward to the State's territorial jurisdiction.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>“Construction” means any clearing, grading, excavation, building, or other action that would affect the natural environment of the coastal area or the commencement of any of these activities. This does not include any activity for the sole purpose of securing biological or geological data or other data for an economic or environmental analysis.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>“Department” means the Department of the Environment.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>“Facility” means:</text>
          <paragraph num="(a)">
            <text>Any pipeline designed to carry crude oil or natural gas ashore from offshore sources;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Any intermediate production terminal or refinery which is designed to process at least 10,000 barrels of crude oil equivalent per calendar day;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Any oil storage facility designed to handle crude oil, and:</text>
            <paragraph num="(i)">
              <text>Whose total design capacity is at least 100,000 barrels,</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Which occupies at least 50 acres, or</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Whose average throughput is at least 10,000 barrels per calendar day;</text>
            </paragraph>
          </paragraph>
          <paragraph num="(d)">
            <text>Any operations base which:</text>
            <paragraph num="(i)">
              <text>Includes port and harbor facilities,</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Occupies at least 25 acres, and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Is designed, constructed, and operated as an assembly area for the storage, handling, and transport of supplies whose next and final destination is any oil and/or gas exploration, development, or production-related operation conducted in the territorial sea, contiguous zone, or high seas area; or</text>
            </paragraph>
          </paragraph>
          <paragraph num="(e)">
            <text>Any fabrication yard which is an assembly operation used for the construction or preparation of petroleum drilling rigs, jackets or platforms, or wellhead installations, whose final destination is installation or operation in the territorial sea, contiguous zone, or high seas area.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(5)">
          <text>“Government agencies” means the government of the United States, the State of Maryland, or any other state, their political subdivisions, units, or instrumentalities, and interstate units.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>“Intermediate production terminal” means a facility which is designed to perform one or more of the following functions:</text>
          <paragraph num="(a)">
            <text>Separation of natural gas from an oil or oil/water mixture or sand from an oil or oil/water mixture;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Dehydration of natural gas;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Pressurization of an oil or oil/water mixture or natural gas;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Extract and treat heavy fractions of natural gas such as butane and propane; or</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Load, offload, or transship crude oil or natural gas in any form.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(7)">
          <text>“Person” includes corporations, companies, associations, firms, partnerships, and joint stock companies, as well as individuals and government agencies.</text>
        </paragraph>
        <paragraph num="(8)">
          <text>“Secretary” means the Secretary of the Environment.</text>
        </paragraph>
        <paragraph num="(9)">
          <text>“Statement” means the economic, fiscal, and environmental statement required by Environment Article, §14-506, Annotated Code of Maryland.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Statement of Purpose.">
      <text>These regulations are promulgated to establish procedures governing applications for the construction of facilities in the coastal area and to provide for the comprehensive review and evaluation of coastal facilities applications.</text>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="General Procedure.">
      <paragraph num="A.">
        <text>A person may not construct, or cause to be constructed, a facility in the coastal area unless he first obtains a permit pursuant to these regulations.</text>
      </paragraph>
      <paragraph num="B.">
        <text>If an application is, in the determination of the Secretary, substantively modified after the review process begins, the application, as modified, shall be processed and evaluated in accordance with these regulations.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Facilities for which on-site construction, excluding site preparation, has legally begun before July 1, 1975, are exempt from the provisions of the Coastal Facilities Review Act.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Contents of Application.">
      <paragraph num="A.">
        <text>A person proposing to construct a facility in the coastal area shall file a written application with the Department.</text>
      </paragraph>
      <paragraph num="B.">
        <text>The application shall contain the information set forth in this regulation.</text>
      </paragraph>
      <paragraph num="C.">
        <text>The application shall contain the applicant's name and business address, and the name, title, and business address of the person or persons authorized to act on behalf of the applicant for the purposes of the application.</text>
      </paragraph>
      <paragraph num="D.">
        <text>The application shall contain a summary description of the project including the purpose of the facility, location, design and operating features, provisions to mitigate aesthetic and environmental impacts, preliminary construction cost figures, and general schedules for the engineering, construction, and activation phases of the project.</text>
      </paragraph>
      <paragraph num="E.">
        <text>The application shall contain general engineering descriptions for all proposed structures.</text>
      </paragraph>
      <paragraph num="F.">
        <text>The application shall contain maps displaying the project as follows:</text>
        <paragraph num="(1)">
          <text>A county-wide map at a scale of 1 inch to 1 mile (1:63,360); this map shall include the number of grids in the Maryland Automated Geographic Information System pertaining to the project site;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>A project location map drawn on a current 7.5 minute topographic quadrangle sheet;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>A tax map showing the site by block and lot numbers, the block and lot numbers and acreage of lots within 200 feet of the site shall be included; the names and addresses of the owners of these adjacent lots shall be listed on a separate sheet;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>An existing site conditions map as follows:</text>
          <paragraph num="(a)">
            <text>A topographic map and hydrographic chart, if applicable, of the site and its surroundings to a distance of 1,000 feet, prepared at a scale no smaller than 1 inch equals 200 feet, with contour levels for the site portion of the map at intervals not greater than 5 feet;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The map shall be accompanied by appropriate text identifying and describing the following items:</text>
            <paragraph num="(i)">
              <text>Boundary lines of the site, with bearings and distances;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>General topography and natural features;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Existing structures and land uses, including open space, within 1,000 feet of the site;</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>Existing easements on and within 1,000 feet of the site, with their location, width, purpose, and ownership:</text>
            </paragraph>
            <paragraph num="(v)">
              <text>Total acreage of the project site and acreage of the contiguous property owned or controlled by the applicant, if the project for which the permit application is made includes only part of this property;</text>
            </paragraph>
            <paragraph num="(vi)">
              <text>Provisions of municipal zoning ordinances, municipal and county master plans, county water and sewer and solid waste plans, State water quality management plans, transportation and school construction plans, solid waste, critical areas, and official maps applicable to the site and the area within 1,000 feet of the site;</text>
            </paragraph>
            <paragraph num="(vii)">
              <text>Public and private wetlands as defined by Environment Article, §16-101, Annotated Code of Maryland, publicly owned lands, flood plains as defined by 24 CFR §1909.1, and forested lands.</text>
            </paragraph>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="G.">
        <text>The application shall contain a completed Board of Public Works master application form if the application is filed in accordance with the Consolidated Permit Procedures of Article 78A, Annotated Code of Maryland.</text>
      </paragraph>
      <paragraph num="H.">
        <text>The application shall contain a detailed project description as follows:</text>
        <paragraph num="(1)">
          <text>A conceptual design including maps, diagrams, and engineering descriptions of each structure; the conceptual design shall contain the following information:</text>
          <paragraph num="(a)">
            <text>The number of acres of the project site owned, leased, or held under option or other similar arrangement;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Existing and proposed buildings, major accessory structures and total land required;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Existing and proposed roads and other transportation facilities such as railroads, entranceways, parking and loading areas, piers, wharves, boat landings, and other port facilities;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Existing and proposed gas and electric utility, drainage, and other rights-of-way other than roads;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Project landscaping features;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Soil erosion and sedimentation control measures;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>Storm water management techniques;</text>
          </paragraph>
          <paragraph num="(h)">
            <text>Improvements to the site and adjacent land including dredging and soil disposal activities; and</text>
          </paragraph>
          <paragraph num="(i)">
            <text>If the project is to be developed in phases, a description of each of the prospective development stages;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Descriptions and general estimates of construction costs, the construction schedule, and construction methods including the following:</text>
          <paragraph num="(a)">
            <text>The total estimated capital cost of the facility;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The number and types of firms and individuals to be employed during construction, estimates of the total construction materials and payroll, and the value of construction materials and services to be purchased in Maryland;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The construction timetable for each major component and for the total project;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>The approximate dates construction will begin and end;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>The construction and building techniques including procedures to be taken before or during construction of proposed facilities such as relocation of homes and commercial or industrial facilities, clearing, surveying, and environmental planning;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>A description of the operations of the completed facility including the following items:</text>
          <paragraph num="(a)">
            <text>A description of the industrial operations;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The goods and services to be produced including the dollar value of goods and services if known;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Estimated annual payroll of the facility; if the facility operations will increase on a phased basis, state the total estimated payroll at each phase;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Estimated effect of the facility upon State, county, and local taxes and depreciation rates for the facility;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>For both the construction and operational phases of the project, the method of transportation (pipeline, rail, water, air, or highway) for moving materials, equipment, and products to and from the facility and the expected size and weight of trucks and volume of daily truck and auto traffic;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>New transportation facilities (pipelines, roads, rail lines, airports, port facilities) required as a result of construction and operation of facility;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>The type of power and fuels to be used during facility operations;</text>
          </paragraph>
          <paragraph num="(h)">
            <text>The type and estimated amount of solid and liquid waste to be produced by facility construction and operation;</text>
          </paragraph>
          <paragraph num="(i)">
            <text>A description of the number and type of employees including:</text>
            <paragraph num="(i)">
              <text>The total number of employees; if the facility operations will increase on a phased basis, state the total for each phase;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>The largest number of employees on a single shift;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>If employment will be seasonal, the estimated number of seasonal employees at the peak season; and</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>The estimated percentage of permanent, and temporary, employees to be hired locally;</text>
            </paragraph>
          </paragraph>
          <paragraph num="(j)">
            <text>The estimated annual amount and dollar value of supplies and services to be purchased in the State during operations;</text>
          </paragraph>
          <paragraph num="(k)">
            <text>Expected date operations will begin;</text>
          </paragraph>
          <paragraph num="(l)">
            <text>Safety provisions for emergency access by police, fire protection, and ambulance services;</text>
          </paragraph>
          <paragraph num="(m)">
            <text>Operating requirements of the facility including an explanation of how the following requirements will be met:</text>
            <paragraph num="(i)">
              <text>Electricity and other energy demands;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Surface, or ground water, or both;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Shoreline access; and</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>Municipal facility improvements and interconnections including water, sewers, highways, and fire services;</text>
            </paragraph>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>Special facility characteristics including the following information;</text>
          <paragraph num="(a)">
            <text>For pipelines:</text>
            <paragraph num="(i)">
              <text>Starting point;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Terminus;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Route;</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>Diameter;</text>
            </paragraph>
            <paragraph num="(v)">
              <text>Total daily throughput capacity;</text>
            </paragraph>
            <paragraph num="(vi)">
              <text>Anticipated operating capacity;</text>
            </paragraph>
            <paragraph num="(vii)">
              <text>Materials to be transported;</text>
            </paragraph>
            <paragraph num="(viii)">
              <text>Operating pressures and temperature;</text>
            </paragraph>
            <paragraph num="(ix)">
              <text>Location of pumping stations;</text>
            </paragraph>
            <paragraph num="(x)">
              <text>Sources of materials to be handled; and</text>
            </paragraph>
            <paragraph num="(xi)">
              <text>Destination of materials to be handled;</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>For intermediate production terminals:</text>
            <paragraph num="(i)">
              <text>Type and industrial purpose of project;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Total daily throughput capacity;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Anticipated operating capacity;</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>Materials to be handled;</text>
            </paragraph>
            <paragraph num="(v)">
              <text>Source, destination, and end use of materials to be handled;</text>
            </paragraph>
          </paragraph>
          <paragraph num="(c)">
            <text>For crude oil storage facilities:</text>
            <paragraph num="(i)">
              <text>Total capacity of structures; and</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Source, destination, and end use of materials to be handled;</text>
            </paragraph>
          </paragraph>
          <paragraph num="(d)">
            <text>For an operations base:</text>
            <paragraph num="(i)">
              <text>Total warehouse area, and office area;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Materials to be handled;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Source, destination, and end use of materials to be handled;</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>Port, highway, and rail traffic estimates; and</text>
            </paragraph>
            <paragraph num="(v)">
              <text>Operating procedures;</text>
            </paragraph>
          </paragraph>
          <paragraph num="(e)">
            <text>For fabrication yards:</text>
            <paragraph num="(i)">
              <text>Source of major materials;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Destination of finished items;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Number of structures to be constructed at one time in the facility;</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>Port, highway, and rail traffic estimate;</text>
            </paragraph>
            <paragraph num="(v)">
              <text>Operating procedures to be employed in the facility;</text>
            </paragraph>
            <paragraph num="(vi)">
              <text>Industrial techniques to be employed in the facility; and</text>
            </paragraph>
            <paragraph num="(vii)">
              <text>Provisions for health, safety, general welfare, and pollution containment including written and schematic information on provisions for occupational safety, fire prevention systems, and pollution containment systems including oil containment capability, water pollution containment capability, and air pollution prevention capacity.</text>
            </paragraph>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="I.">
        <text>The application shall contain, for both the construction and operation phases of the project, an identification of potential sources of impacts, including noise, visual, air and water pollution, and other environmental impacts caused by the project.</text>
      </paragraph>
      <paragraph num="J.">
        <text>The application shall contain a summary of the probable impacts of the project in at least the following areas:</text>
        <paragraph num="(1)">
          <text>Geology and soils of the site and surrounding region;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Hydrology of the site and surrounding region;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Vegetation of the site and surrounding region;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Fish, shellfish, and wildlife of the site and surrounding region;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Historic, archeological, and cultural resources of the surrounding regions;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Air quality;</text>
        </paragraph>
      </paragraph>
      <paragraph num="K.">
        <text>The application shall contain a description of the status of all required federal licenses, permits, and other approvals, with attached supporting material, if appropriate.</text>
      </paragraph>
      <paragraph num="L.">
        <text>The application shall contain a discussion of the need for the facility in the light of feasible alternatives available to the applicant, concerning, in particular:</text>
        <paragraph num="(1)">
          <text>The demand for the goods and services to be provided by the facility, including a discussion of the means employed to determine present and future demands;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The need for the construction of this particular facility, including:</text>
          <paragraph num="(a)">
            <text>An inventory of similar existing facilities operated by or available to the applicant within a reasonable service region and a determination of their available capacity and anticipated expansion of capacity, if any; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A documentation of why this identified available capacity or expansion of capacity will not suffice to meet the demand for the service to be provided by the proposed facility;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>Alternatives to the facility, including:</text>
          <paragraph num="(a)">
            <text>A concise description of economically and environmentally feasible alternative facilities, facility locations, and industrial processes available to the applicant;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>An evaluation of the advantages and disadvantages, in terms of operating requirements, employment levels, pollution loads, environmental quality costs, and economic impact on local government of each identified alternative; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A comparison of the proposed facility with each of the alternatives identified including an analysis of the environmental and economic advantages and disadvantages of each alternative.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="M.">
        <text>Completed Application Forms for Licenses or Permits.</text>
        <paragraph num="(1)">
          <text>Copies of the following completed application forms for licenses or permits shall be attached if they have been completed:</text>
          <paragraph num="(a)">
            <text>Public and private wetlands;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Oil handler's;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Surface water appropriations;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Ground water appropriations;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Waterway construction and obstruction;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Water discharge (MPDES); and</text>
          </paragraph>
          <paragraph num="(g)">
            <text>All other applicable State permits.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Application forms completed after initiation of procedures pursuant to these regulations shall be forwarded at the time of completion.</text>
        </paragraph>
      </paragraph>
      <paragraph num="N.">
        <text>The applicant shall furnish any other information determined by the Department to be necessary for processing the application.</text>
      </paragraph>
      <paragraph num="O.">
        <text>The applicant shall certify that all the information contained in the application is true, complete, and accurate to the best of the applicant's knowledge.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Application Distribution.">
      <paragraph num="A.">
        <text>The applicant shall furnish at least 12 copies of the application to the Department.</text>
      </paragraph>
      <paragraph num="B.">
        <text>The copies shall be distributed as follows:</text>
        <paragraph num="(1)">
          <text>Three copies shall be forwarded to each county and incorporated municipality in which the facility is to be located;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Six copies shall be retained by the Secretary and distributed to State agencies;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Two copies shall be placed on open file in public buildings in the county in which the project is to be located; and</text>
        </paragraph>
        <paragraph num="(4)">
          <text>One copy shall be placed on open file at the offices of the Department of the Environment.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Upon receipt of a completed application, the Department promptly shall place a notice in the Maryland Register that an application has been received.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".06" heading="Local Certification.">
      <paragraph num="A.">
        <text>An application may not be processed further until the county in which the facility is to be located or in which the pipeline is to terminate has certified to the Secretary one of the following:</text>
        <paragraph num="(1)">
          <text>All local land use classifications including zoning, variances, special exceptions, or conditional uses necessary for the location and operation of the facility have been or will be granted;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The county has postponed certification pending completion of the statement; or</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Local land-use classifications necessary for the location and operation of the facility have been or will be denied.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>If there has been no local government decision pursuant to §A of this regulation within 60 days after notice that an application has been received appears in the Maryland Register, then the Secretary may assume that the local government has stayed its decision, pursuant to §A(2), and may proceed with preparation of the statement.</text>
      </paragraph>
      <paragraph num="C.">
        <text>If the county certifies its approval or stays certification, then the Secretary shall proceed to process the application. If the county notifies the State of its denial, then the application process shall terminate.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Once the statement is complete, but before the Secretary's decision, a county that has stayed its decision pursuant to §A(2) of this regulation or by operation of §B of this regulation shall certify to the Secretary one of the following:</text>
        <paragraph num="(1)">
          <text>All local land-use classifications including zoning, special exceptions, variances, conditional uses, and other permits or required local government actions necessary for the location or operation of the facility have been granted;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The county supports the location and operation of the proposed facility and reasonably expects to grant local land-use classifications including zoning, special exceptions, variances, conditional uses, and other permits or required local government actions necessary for the location and operation of the facility; or</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Local land-use classifications necessary for the location or operation of the facility have been or will be denied.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>If the county certifies its approval pursuant to §D(1) or (2) of this regulation, the Secretary shall continue to process the application. If the county notifies the State of its denial, then the application process shall terminate.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".07" heading="Statement.">
      <paragraph num="A.">
        <text>Once an application has been received and reviewed by State agencies, the Secretary has received the comments of the State agencies, and the county in which the proposed facility is proposed to be located has either certified its approval or stayed certification, the Secretary, after consulting with the applicant, appropriate governmental agencies, and interested parties, shall select appropriate parties to prepare an economic, fiscal, and environmental impact statement. The Coastal Zone Management Program shall coordinate preparation of the statement. The purpose of the statement is to develop and assemble in one document material, facts, and analyses to assist the Secretary and the local government in making a decision on whether to grant, grant conditionally, or deny a permit.</text>
      </paragraph>
      <paragraph num="B.">
        <text>To the maximum extent possible, the statement shall incorporate and utilize studies, inventories, and other work relevant to the facility and prepared pursuant to any law including but not limited to the National Environmental Policy Act. The Secretary shall determine the applicability of these materials.</text>
      </paragraph>
      <paragraph num="C.">
        <text>The statement shall be filed with the Department within 6 months of the Secretary's designation unless the Secretary extends the period of preparation up to but not more than an additional 12 months for good cause. If the period of preparation is extended, the Secretary shall notify the applicant and the county by letter and shall place a notice in the Maryland Register.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Contents of Statement.</text>
        <paragraph num="(1)">
          <text>Upon receipt of the advisory comments of other State agencies, the Secretary shall set forth the minimum contents of each statement.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>All statements shall include the following:</text>
          <paragraph num="(a)">
            <text>An inventory of existing economic and environmental conditions at the project site and in the immediate area;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A project description of what is to be constructed, and the manner and construction schedule and the method of construction;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A complete description of the proposed facility including at least its anticipated size, effluent load, and production levels;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>An assessment of the probable economic, fiscal, and environmental impact of the project upon the natural environment of the project site, coastal area, and the immediate area;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Recommendations for minimizing any adverse economic, fiscal, or environmental impacts;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>An evaluation of the need for the facility and the relative merits of other possible sites;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>In the case of a refinery, a description of the manner of transportation of the feed stock and the product of the crude oil;</text>
          </paragraph>
          <paragraph num="(h)">
            <text>Expected secondary impacts of constructing the facility, including new residential housing, schools, commercial services, and additional public services;</text>
          </paragraph>
          <paragraph num="(i)">
            <text>Probable adverse environmental impacts of the project that cannot be avoided including irretrievable commitment of resources, which shall include a description of significant secondary consequences and cumulative and long-term effects of the project on the environment and the natural resources base, and the extent to which the project curtails the range of beneficial uses of the environment.</text>
          </paragraph>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".08" heading="Public Review.">
      <paragraph num="A.">
        <text>The Department shall make the statement available for public review, and shall distribute the statement as provided by Regulation .05 of this chapter.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Within 60 days of completion of the statement, the Department shall hold at least one public hearing in the county in which the facility or any part of it is to be located. The purpose of the hearing is to solicit the views of the public concerning the permit application. Comments prepared by the Department or other State agencies, any proposed permits to be issued by a State agency to the applicant, any condition proposed by the Department before granting a permit, and any other pertinent information shall be made available to the public before the public hearing.</text>
      </paragraph>
      <paragraph num="C.">
        <text>The Department shall give notice of hearing by placing a public notice in the classified section of appropriate newspapers of Statewide and local circulation and in the Maryland Register. Notice shall also be given to State agencies and local governments.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".09" heading="Permit Evaluation.">
      <paragraph num="A.">
        <text>After receiving advisory comments and recommendations, but not later than 90 days following the completion of the public hearing, and after local certification pursuant to Regulation .06A(1), D(1), or D(2) of this chapter, the Secretary shall grant, grant conditionally, or deny the permit.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Secretary's Decision.</text>
        <paragraph num="(1)">
          <text>In making his decision, the Secretary shall consider the application, the statement, the advisory comments, the public hearing record, and any other information which may be available to him.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The Secretary's decision shall be delivered in writing to the applicant and the county and incorporated municipality in which the facility is to be located.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The Secretary's decision shall be based upon a determination of whether the facility meets the following requirements:</text>
          <paragraph num="(a)">
            <text>Conforms with and meets all applicable air, water, noise, and solid waste laws of the State as determined and certified in writing by the appropriate State units with jurisdiction over these laws;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Conforms with adopted or approved county or local land use planning, the official county or local comprehensive zoning map;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Conforms with the State development plan, when this plan has been lawfully approved and adopted;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Would have no material adverse effect upon the natural environment of the area, its scenic or natural beauty, rare or irreplaceable natural resources, or unique historic sites;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Would not be located or constructed so as to have a material adverse effect upon the public health, safety, or welfare;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Would not be a potential or immediate undue burden on the water supply of the site or region;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>Would not materially contribute to an extant level of undue environmental degradation or resource exhaustion;</text>
          </paragraph>
          <paragraph num="(h)">
            <text>Conforms with any coastal zone management program developed by the State pursuant to the Federal Coastal Zone Management Act of 1972 as amended;</text>
          </paragraph>
          <paragraph num="(i)">
            <text>Would have no material adverse effect upon critical areas identified and designated pursuant to State Finance and Procurement Article, Title 5, Subtitle 6, and Article 66C, §3.05, Annotated Code of Maryland;</text>
          </paragraph>
          <paragraph num="(j)">
            <text>Would not impose, directly or indirectly, a substantial burden on existing State, regional, or county public facilities beyond their respective capacities, or that new public facilities, if necessary, would be either:</text>
            <paragraph num="(i)">
              <text>Completed in time to serve the facility; or</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Adequate to serve the facility without causing overloading of the public facilities.</text>
            </paragraph>
          </paragraph>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".10" heading="Duration of Validity of a Permit.">
      <paragraph num="A.">
        <text>Plans and specifications in the permit and conditions imposed by a permit shall remain in full force and effect so long as the proposed facility, or any portion of it, is in existence unless the permit is modified. A permit is subject to suspension and revocation for violation of its terms and conditions or for violations of the Coastal Facilities Review Act.</text>
      </paragraph>
      <paragraph num="B.">
        <text>A permit shall be valid authority to begin construction of a facility within 2 years from the date of issuance of the permit. Upon written request from the permittee, and if the Department determines that the project has not been substantively modified, the Department may extend this authority for 1 year. Not more than three of these 1-year extensions may be approved. If construction does not commence and continue within this 2-year period and no extension is granted, then the permit shall lapse.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".11" heading="Fees.">
      <text>The applicant shall bear the cost of processing an application and the cost of preparing a statement, according to the following schedule:</text>
      <paragraph num="A.">
        <text>All applications shall be accompanied by an application fee of $500, which shall be retained by the Department and used to cover initial application processing costs. Processing costs shall be computed at the rate of $15 per man-hour. Costs in excess of $500 shall be billed to the applicant on a monthly basis. An applicant may not be required to pay more than $5,000 processing costs for any one application unless an original application is substantively modified.</text>
      </paragraph>
      <paragraph num="B.">
        <text>The applicant shall pay the Department at the rate of $15 per man-hour for in-house time spent by the Department in the preparation of a statement. The applicant shall be billed on a monthly basis for these costs.</text>
      </paragraph>
      <paragraph num="C.">
        <text>The applicant shall be responsible for any and all contractual costs incurred by the Department in preparing a statement. The applicant shall be notified by the Department of anticipated contractual costs before signing any contract. The applicant shall remit to the Department on a monthly basis an amount sufficient to cover estimated contractual costs to be incurred during the following month.</text>
      </paragraph>
      <paragraph num="D.">
        <text>If the applicant should withdraw his application at any time during preparation of the statement, he shall be responsible only for costs incurred up to and through the withdrawal date and any costs incurred in terminating the application process.</text>
      </paragraph>
      <paragraph num="E.">
        <text>The Department shall keep accurate records of all administrative and contractual costs. These records shall be open for inspection by the applicant upon reasonable notice to the Department.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Environment Article, §14-503, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective: April 13, 1977 (4:8 Md. R. 641)</annotation>
      <annotation type="History" subtype="Administrative History">Regulations .06 and .07 amended effective February 10, 1978 (5:3 Md. R. 138)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter recodified from COMAR 08.13.03 to 26.22.01, June 1996</annotation>
    </annotations>
  </chapter>
</subtitle>