  <paragraph num="A.">
    <text>Application Procedures.</text>
    <paragraph num="(1)">
      <text>A person proposing to establish and operate a mitigation bank shall submit a mitigation bank application on a form provided by the Department.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The application shall meet the requirements of COMAR 26.23.02.01B(6).</text>
    </paragraph>
    <paragraph num="(3)">
      <text>A mitigation bank concept plan is submitted with the application and includes:</text>
      <paragraph num="(a)">
        <text>Drawings at a scale equal to 1 inch equals 200 feet or other scale approved by the Department, and showing existing topography, nontidal wetland boundaries and buffers, and 100-year floodplain boundaries, if applicable;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>A vicinity map of the proposed mitigation bank site;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Proposed acreage and type of nontidal wetlands to be established in the bank;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>A description of methods of establishment of nontidal wetlands;</text>
      </paragraph>
      <paragraph num="(e)">
        <text>The proposed water source;</text>
      </paragraph>
      <paragraph num="(f)">
        <text>A description of proposed earth disturbance necessary;</text>
      </paragraph>
      <paragraph num="(g)">
        <text>A preliminary assessment of impact, if any, on existing nontidal wetlands, buffers, and 100-year floodplains;</text>
      </paragraph>
      <paragraph num="(h)">
        <text>A proposed mechanism to protect the mitigation bank site in perpetuity, including easements, covenants, deed restrictions, or similar means approved by the Department;</text>
      </paragraph>
      <paragraph num="(i)">
        <text>As applicable, information regarding consistency with natural resource management plans, approved watershed plans, forest conservation, local growth management policies, and local comprehensive plans; and</text>
      </paragraph>
      <paragraph num="(j)">
        <text>Other information required by Regulation .05C of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>The applicant shall provide other pertinent information as required by the Department.</text>
    </paragraph>
    <paragraph num="(5)">
      <text>The Department shall render a decision on the completeness of the mitigation bank application within 45 days of receipt.</text>
    </paragraph>
    <paragraph num="(6)">
      <text>The Department may extend the time period for review of the mitigation bank application due to:</text>
      <paragraph num="(a)">
        <text>Inclement weather conditions; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Additional review required by other State, federal, or local agencies.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Public Notice and Public Informational Hearing.</text>
    <paragraph num="(1)">
      <text>The Department may issue a public notice for a proposed mitigation bank less than 5 acres in size.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>After the Department has determined that an application for a proposed mitigation bank greater than 5 acres in size is complete, the Department shall issue, at the applicant's expense, a public notice in accordance with COMAR 26.23.02.02G(2) and (3).</text>
    </paragraph>
    <paragraph num="(3)">
      <text>If requested, a public informational hearing shall be conducted in accordance with COMAR 26.23.02.02H.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Based on information presented at the public informational hearing, the applicant may be required to submit additional information.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>Mitigation Banking Agreement.</text>
    <paragraph num="(1)">
      <text>A mitigation banking agreement shall be developed after the Department approves a mitigation banking application.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The Department and the applicant shall execute a mitigation banking agreement before:</text>
      <paragraph num="(a)">
        <text>Construction of the mitigation bank; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Consideration by the Department of the use of the mitigation credits by applicants.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>At the Department's discretion, a mitigation banking agreement may include:</text>
      <paragraph num="(a)">
        <text>Construction plans and specifications developed in accordance with Regulation .05C(2) of this chapter;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Specifications for:</text>
        <paragraph num="(i)">
          <text>A bond or alternate form of security, as approved by the Department; or</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>A remedy to be imposed on a government agency responsible for a government-operated mitigation bank, upon failure to perform remediation;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(c)">
        <text>Performance standards to demonstrate anticipated success of the mitigation bank, including:</text>
        <paragraph num="(i)">
          <text>Sufficiency of hydrology to sustain a nontidal wetland;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>An interim standard of a minimum of 45 percent coverage of planted or naturally occurring plant species;</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>A final standard of a minimum of 85 percent coverage of planted or naturally occurring plant species within a time frame specified by the Department which may not exceed the term of the monitoring period specified in Regulation .04A of this chapter; and</text>
        </paragraph>
        <paragraph num="(iv)">
          <text>Evidence to document that the mitigation bank is providing or will provide specific nontidal wetland functions;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(d)">
        <text>Provisions for post-construction monitoring and maintenance of the mitigation bank consistent with Regulation .04A of this chapter;</text>
      </paragraph>
      <paragraph num="(e)">
        <text>The executed instrument to protect the mitigation bank in perpetuity;</text>
      </paragraph>
      <paragraph num="(f)">
        <text>Bank operation and maintenance procedures;</text>
      </paragraph>
      <paragraph num="(g)">
        <text>Bank operator responsibilities;</text>
      </paragraph>
      <paragraph num="(h)">
        <text>Remediation procedures;</text>
      </paragraph>
      <paragraph num="(i)">
        <text>Accounting and reporting requirements;</text>
      </paragraph>
      <paragraph num="(j)">
        <text>Monitoring requirements;</text>
      </paragraph>
      <paragraph num="(k)">
        <text>Mitigation bank close-out procedures;</text>
      </paragraph>
      <paragraph num="(l)">
        <text>Procedures for termination of the agreement; and</text>
      </paragraph>
      <paragraph num="(m)">
        <text>Other terms agreed upon by the bank operator and the Department.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>The bank operator shall construct, operate, and maintain the mitigation bank according to the terms of the mitigation banking agreement.</text>
    </paragraph>
    <paragraph num="(5)">
      <text>The Department shall approve, in writing, all revisions, amendments, or modifications to the mitigation banking agreement.</text>
    </paragraph>
    <paragraph num="(6)">
      <text>The bank operator shall notify the Department upon completion of construction of the mitigation bank.</text>
    </paragraph>
    <paragraph num="(7)">
      <text>Within 60 days of completion of construction, the bank operator shall submit to the Department:</text>
      <paragraph num="(a)">
        <text>As-built drawings with post-construction contours; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Drawings showing actual planting, which are attached to and made a part of the mitigation banking agreement.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(8)">
      <text>The bank operator shall allow representatives or agents of the Department to enter the mitigation bank at any time during or after construction to conduct inspections and to assess the success of the mitigation bank.</text>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>Timing of Sale of Mitigation Credit and Approval of Mitigation Bank Use.</text>
    <paragraph num="(1)">
      <text>The bank operator may select the time to begin sale of credits.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The sale of credits by a bank operator may not imply approval of the use of those credits by the Department for specific projects.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>The Department may approve use of not more than 1/2 of the acreage in a mitigation bank before the end of two full growing seasons after construction, based on approval by the Department of:</text>
      <paragraph num="(a)">
        <text>Executed mitigation banking agreement;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>As-built plans showing completed site construction, preparation, and contouring;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Executed mechanism to protect the mitigation bank in perpetuity; and</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Fulfillment of bonding requirements, if applicable.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>The Department may approve use of the remaining 1/2 of the acreage after two full growing seasons have elapsed, if remediation is not required and the interim performance standards specified in the mitigation banking agreement have been met.</text>
    </paragraph>
    <paragraph num="(5)">
      <text>The Department shall advise the bank operator and applicants proposing to use credits of the Department's approval of the bank.</text>
    </paragraph>
    <paragraph num="(6)">
      <text>The Department may approve use of mitigation credits as partial fulfillment of a permittee's mitigation requirement.</text>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>Accounting and Reporting Requirements.</text>
    <paragraph num="(1)">
      <text>Within the time frames allowed in the mitigation banking agreement, the bank operator shall submit to the Department for each transaction the:</text>
      <paragraph num="(a)">
        <text>Name and address of the person purchasing or returning credits;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Date of the transaction;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Amount and type of wetland acreage to be used as credit; and</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Project name, location, and the Department's application processing number, if applicable, for which use of mitigation credit is proposed.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>A government agency responsible for a government operated mitigation bank shall submit the name and address of the agency utilizing credits, the name of the contact person, and the information specified in §E(1)(b)—(d) of this regulation.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>The bank operator and the Department shall jointly record withdrawal of the acreage approved for use by an applicant.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Mitigation credit will be withdrawn from the mitigation bank in the order approved by the Department.</text>
    </paragraph>
    <paragraph num="(5)">
      <text>For each year of operation, a summary of all activities relating to the sale or transfer of mitigation credits is submitted to the Department within 30 days after December 31 of each calendar year.</text>
    </paragraph>
    <paragraph num="(6)">
      <text>The bank operator shall notify the Department if the bank operator wishes to cease consideration of areas representing unsold or unused credits as part of the mitigation bank.</text>
    </paragraph>
    <paragraph num="(7)">
      <text>Mitigation credit withdrawn for a project anticipated to be authorized by the Department under this subtitle is returned to the mitigation bank if the Department:</text>
      <paragraph num="(a)">
        <text>Denies the authorization;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Authorizes impacts that are less than the amount anticipated; or</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Requires mitigation by a method other than use of the mitigation credit.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="F.">
    <text>Remediation.</text>
    <paragraph num="(1)">
      <text>The Department may require remediation at any time before the end of the monitoring period to ensure compliance with the performance standards specified in the mitigation banking agreement.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>To determine if remediation is necessary, the Department may require that specific data be collected and submitted by the bank operator.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Remediation required by the Department is directly related to ensuring that the performance standards specified in the mitigation banking agreement will be met.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>The Department may withhold or suspend approval of use of credits in the bank until remediation is completed to the Department's satisfaction.</text>
    </paragraph>
    <paragraph num="(5)">
      <text>The Department may consider continuing to approve use of credits in the bank for that portion of the bank not requiring remediation.</text>
    </paragraph>
    <paragraph num="(6)">
      <text>If, after a period to be specified in a mitigation banking agreement, the Department determines that a government agency responsible for a government-operated mitigation bank has not performed remediation, the remedy specified in the mitigation banking agreement is imposed.</text>
    </paragraph>
  </paragraph>
  <paragraph num="G.">
    <text>Close Out of Mitigation Banks.</text>
    <paragraph num="(1)">
      <text>The Department and a bank operator may close out a mitigation bank when:</text>
      <paragraph num="(a)">
        <text>All credits have been withdrawn;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Monitoring has been completed to the Department's satisfaction;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Remediation, if required by the Department, has been completed to the Department's satisfaction;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Protection in perpetuity has been established; and</text>
      </paragraph>
      <paragraph num="(e)">
        <text>The bond or alternate form of security, if applicable, has been released.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>The bank operator shall notify the Department in writing to request confirmation of the decision to close out the mitigation bank.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>The Department shall confirm the close out within 45 days of receipt of the request, unless additional information is needed or the conditions in §G(1) of this regulation have not been met.</text>
    </paragraph>
  </paragraph>