<chapter num="02" heading="Permits and Licenses" title_num="26" subtitle_num="24">
  <regulation prefix="Regulation" num=".01" heading="General Requirements for a State Tidal Wetlands License or Private Tidal Wetlands Permit.">
    <paragraph num="A.">
      <text>License or Permit Required. Except as set forth in §C of this regulation, before beginning any work, a person who proposes to construct or reconstruct structures, or to dredge or fill a State or private tidal wetland, shall obtain a:</text>
      <paragraph num="(1)">
        <text>License from the Board; or</text>
      </paragraph>
      <paragraph num="(2)">
        <text>License, general license, general permit, or permit from the Department.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Uses and Activities Prohibited on State or Private Tidal Wetlands Without a License or Permit. Except when authorized, a person may not:</text>
      <paragraph num="(1)">
        <text>Fill, place, dump, or discharge on tidal wetlands any:</text>
        <paragraph num="(a)">
          <text>Loam, peat, sand, gravel, soil, or other similar substance, or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Trash, garbage, debris, junk, or other polluting substance;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Drain, excavate, or dredge the tidal wetlands encompassed by this subtitle, or remove from the tidal wetlands loam, peat, sand, gravel, soil, or other similar substance;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Construct any structure in, on, over, or under tidal wetlands; or</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Perform an act or use involving tidal wetlands in a manner which would destroy the natural vegetation or existing patterns of tidal flow, or alter the natural and beneficial character of the tidal wetland.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Exemptions from a State Tidal Wetlands License and a Private Tidal Wetlands Permit. The following activities are exempted from the requirement to obtain a license from the Board or a license, general license, general permit, or permit from the Department under this subtitle:</text>
      <paragraph num="(1)">
        <text>Dredging of seafood products by any licensed operator including normal leased bottom activities permitted under Natural Resources Article, Title 4, Subtitle 11, Annotated Code of Maryland, and COMAR 08.02.08.12, or the harvesting of submerged aquatic vegetation provided the root system is not affected;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Trapping, hunting, fishing, and catching shellfish, if legally permitted;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Mosquito control and abatement projects as approved by the Department of Agriculture;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Improvement of agricultural drainage ditches as approved by the Department of Agriculture;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Routine maintenance, repair, or replacement of a highway structure, pier, boathouse, a structure on a pier, bulkhead, revetment, tidal impoundment dike, water control structure, aboveground transmission facility, agricultural drainage ditch, or highway drainage ditch when the existing structure is functional and there is no increase in the original length, width, height, or channelward encroachment;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Channel and harbor navigation aids, if approval has been granted by the United States Coast Guard;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Private piers that meet the criteria in COMAR 26.24.04.02;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Control of exotic plant species such as Phragmites australis, if a toxic materials permit under COMAR 26.08.03.02 is obtained;</text>
      </paragraph>
      <paragraph num="(9)">
        <text>Temporary installation of bass spawning boxes from March 1 through June 15 annually outside of marked navigation channels.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Application Requirements.">
    <paragraph num="A.">
      <text>Who May Apply. An applicant for a license or permit is a person:</text>
      <paragraph num="(1)">
        <text>With a riparian interest in private tidal wetlands or upland adjacent to State tidal wetlands, or an agent designated by the person with riparian interest; or</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Seeking approval for navigation, mining, aquaculture, archeology, or similar projects in tidal wetlands.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Application Form.</text>
      <paragraph num="(1)">
        <text>The application form shall be a joint federal and State application for the regulation of activities in tidal wetlands in Maryland.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>An applicant for a tidal wetlands license or permit shall submit all of the information required by the Department in a manner and form acceptable to the Department before final action on the application is taken.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>For additional information requirements for specific project types, see COMAR 26.24.03 and 26.24.04.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The application form is available at the following government agencies:</text>
        <paragraph num="(a)">
          <text>Department of the Environment;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>U. S. Army Corps of Engineers, Baltimore District;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>An agency designated by each county or municipality; or</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Department of the Environment, Water Management Administration.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>The person who signs an application form shall be:</text>
        <paragraph num="(a)">
          <text>An individual or an individual's authorized agent;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>An officer or authorized agent of a corporation;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>An authorized official of a State or local government; or</text>
        </paragraph>
        <paragraph num="(d)">
          <text>An authorized member of an association or partnership.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>The person who signs an application is responsible for the truth, accuracy, and completeness of all information in the application.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>The Department shall acknowledge receipt of an application in writing by regular mail, and shall advise the applicant of the public notice requirements under COMAR 26.24.01.04.</text>
    </paragraph>
    <paragraph num="D.">
      <text>The Department shall review an application to determine whether it is complete for processing. An application is complete if it contains all the information required in this subtitle. The Department shall notify an applicant within 45 days by telephone or in writing of the additional information required in an incomplete application. If the Department fails to notify an applicant within 45 days, an application is considered complete. The Department may require additional information from an applicant as a result of the administrative review process.</text>
    </paragraph>
    <paragraph num="E.">
      <text>For purposes of an application, mean high water and mean low water are:</text>
      <paragraph num="(1)">
        <text>Referenced in feet to a benchmark elevation based upon:</text>
        <paragraph num="(a)">
          <text>The National Geodetic Vertical Datum of 1929 (NGVD) which is incorporated by reference under 41 FR 20202 (1976);</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The North American Vertical Datum of 1988 (NAVD) which is incorporated by reference under 48 FR 50784 (1983); or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A benchmark established and documented by an applicant and approved by the Department;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Determined using one of the following methods:</text>
        <paragraph num="(a)">
          <text>Control tide station data as published by the U. S. Department of Commerce, National Oceanic and Atmospheric Administration;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Derivation of the equivalent high water datum using a comparison of observational records with control tide station data as published by the U. S. Department of Commerce, National Oceanic and Atmospheric Administration; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>An evaluation of the project site conditions based upon the following parameters:</text>
          <paragraph num="(i)">
            <text>Predicted tide range elevations,</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Meteorologic conditions,</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Vegetation and other biological factors at the site including barnacles and algae lines, and</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Physical indicators at the site such as rack lines, stain marks on nearby structures, and beach particle sorting.</text>
          </paragraph>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="F.">
      <text>The Department may require an applicant to engage a professional engineer, licensed under Maryland law, to certify that the design meets all of the requirements of the Department. This requirement may apply to projects including:</text>
      <paragraph num="(1)">
        <text>Shore erosion control structures; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Dredge material placement sites.</text>
      </paragraph>
    </paragraph>
    <paragraph num="G.">
      <text>The Department may require project plans to include a bathymetric survey that is referenced to a benchmark based on the NGVD of 1929 or NAVD of 1988, or a benchmark established and documented by an applicant and approved by the Department. All survey and topographic information shall be referenced to 0.0 mean low water.</text>
    </paragraph>
    <paragraph num="H.">
      <text>Other Approvals.</text>
      <paragraph num="(1)">
        <text>The Department may suspend processing of an application for a structure or activity if the application is inconsistent with State, federal, or local land use requirements, including federal tidal wetlands authorizations under §404 of the Clean Water Act of 1992 and §10 of the Rivers and Harbors Act of 1899, critical area, zoning, special exception, variance, or conditional use approvals. The Department will make these consistency determinations in cooperation with the appropriate State, federal, and local regulatory agencies. Project approval under this subtitle does not relieve a licensee or permittee of the need to obtain other approvals that may be required.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A person shall obtain a permit to engage in aquaculture activities under COMAR 08.02.14 before the Department will accept an application for construction of an aquaculture facility in tidal wetlands.</text>
      </paragraph>
    </paragraph>
    <paragraph num="I.">
      <text>An applicant shall allow reasonable access for inspection of the project site by representatives of the Department.</text>
    </paragraph>
    <paragraph num="J.">
      <text>An applicant may request in writing, at the time an application is submitted or as soon as possible, that certain information submitted as part of an application not be disclosed. The Department shall determine if the information is confidential under State Government Article, Title 10, Subtitle 6, Annotated Code of Maryland, and other applicable law. If the Department denies a request for nondisclosure, an applicant may withdraw the application or appeal the Department's determination under applicable law. If an applicant withdraws an application, the Department shall, at the request of the applicant, return any documents claimed to be confidential.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="Criteria for Evaluating Tidal Wetlands License or Permit Applications.">
    <paragraph num="A.">
      <text>Evaluation Criteria.</text>
      <paragraph num="(1)">
        <text>The criteria in this regulation are presented to assist in preparing an application and to provide a consistent basis for recommendations and decisions for licenses or permits.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>As the basis for a recommendation or final decision, including approval, denial, suspension, or modification of a license or permit, the Department shall take into account ecological, economic, developmental, recreational, and aesthetic values of tidal wetlands in order to preserve tidal wetlands and prevent their despoliation and loss.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>When reviewing an application for a license, the Department considers the proprietary interests of the Board over State tidal wetlands.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Application Evaluation. In evaluating an application, the Department shall consider the degree to which:</text>
      <paragraph num="(1)">
        <text>Dredging and filling activities can be avoided or minimized;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The proposed activity is water-dependent;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The proposed activity will alter or destroy tidal wetlands, including a determination of how the proposed project will:</text>
        <paragraph num="(a)">
          <text>Destroy or adversely affect the value of the tidal wetlands as a source of nutrients or habitat for finfish, crustaceans, mollusks, or wildlife of significant economic or ecologic value,</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Affect potential habitat areas such as historic spawning and nursery grounds for anadromous and semianadromous fisheries species and shallow water areas suitable to support populations of submerged aquatic vegetation,</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Eliminate or substantially reduce marine commerce, recreation, and aesthetic enjoyment,</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Affect the natural ability of tidal wetlands to reduce flood damage and adversely affect the public health and welfare, and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Substantially reduce the capacity of tidal wetlands to trap sediment, and result in increased silting of channel and harbor areas to the detriment of free navigation;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>The proposed activity would alter natural water flow, water temperature, water quality, and natural tidal circulation regimes;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The proposed activity would alter littoral drift;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>The proposed activity enhances the aquatic environment;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>The proposed activity would impact local, regional, and State economic conditions;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>The proposed activity is consistent with State, federal, and local land use plans and laws, including Critical Area laws;</text>
      </paragraph>
      <paragraph num="(9)">
        <text>Alternatives for the disposal of dredged material have been explored;</text>
      </paragraph>
      <paragraph num="(10)">
        <text>The natural, scenic, historic property, and aesthetic values can be retained or enhanced;</text>
      </paragraph>
      <paragraph num="(11)">
        <text>The proposed activity provides facilities for the proper handling of storm water runoff and sanitary wastes;</text>
      </paragraph>
      <paragraph num="(12)">
        <text>Danger may arise because of the location of proposed structures from hurricanes, floods, sea level rise, or other determinable and periodically recurring natural hazards;</text>
      </paragraph>
      <paragraph num="(13)">
        <text>Navigational safety is affected;</text>
      </paragraph>
      <paragraph num="(14)">
        <text>The activity benefits the public, if applicable;</text>
      </paragraph>
      <paragraph num="(15)">
        <text>Shore erosion is controlled;</text>
      </paragraph>
      <paragraph num="(16)">
        <text>Maintenance and operation of the proposed project is assured;</text>
      </paragraph>
      <paragraph num="(17)">
        <text>Recreational and navigational access to beaches and waters of the State is provided;</text>
      </paragraph>
      <paragraph num="(18)">
        <text>The proposed activity would alter the scenic and wild qualities of a designated State scenic and wild river; and</text>
      </paragraph>
      <paragraph num="(19)">
        <text>The proposed activity would impact historic waterfowl staging areas and colonial bird-nesting sites.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="General Tidal Wetlands License.">
    <paragraph num="A.">
      <text>The Board shall issue a general wetlands license for those activities proposed in State tidal wetlands listed in §B of this regulation. A person proposing an activity in State tidal wetlands under the general wetlands license shall apply to the Department. The Department shall consider the ecological, economic, developmental, recreational, and aesthetic values of the proposed project and determine if the proposed project qualifies under the general wetlands license. If a project qualifies for a general wetlands license and does not require mitigation under COMAR 26.24.05.01, the Department may issue the authorization directly to the applicant.</text>
    </paragraph>
    <paragraph num="B.">
      <text>General Wetlands License Projects. Projects which qualify for approval under the general license include projects to:</text>
      <paragraph num="(1)">
        <text>Add stone or broken concrete to a revetment or channelward of a bulkhead if the stone or broken concrete extends not more than 10 feet channelward of the existing structure;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Emplace a revetment for shore erosion control only if it is less than 500 feet in length and it is aligned not more than 10 feet channelward of the mean high water line;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Fill near shore shallow water not more than 35 feet channelward of the mean high water line only if the fill area is less than 500 feet in length and parallel to the upland for the purpose of shore erosion control by tidal vegetated wetland creation;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Maintenance dredge a mooring, boat ramp, or travel lift slip with an area of 1,500 square feet or less and remove 100 cubic yards or less of material, if the licensee complies with the water quality certification required under COMAR 26.08.02;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Reconfigure an existing marina if there is no dredging or no increase in channelward encroachment beyond existing piers and associated structures;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Construct a boat ramp not more than 12 feet wide and 30 feet channelward of the mean high water line;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Armor or strengthen bridges or causeways when the activity extends not more than 10 feet from the existing structure, requires no dredging, and does not impede the flow of the waterway;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Create a new discharge of storm water runoff within 1,000 feet landward of the tidal wetlands boundary, if the drainage system directly discharges to tidal waters and employs stormwater control measures to manage runoff for rate and water quality according to State and local standards which include measures:</text>
        <paragraph num="(a)">
          <text>Designed to control erosive velocities to tidal waters of wetlands, and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Required under COMAR 27.01.01 and 27.02.01 and a State-approved critical area program of a local jurisdiction;;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(9)">
        <text>Clear debris and windfalls from shorelines without dredging State tidal wetlands;</text>
      </paragraph>
      <paragraph num="(10)">
        <text>Install temporary monitoring or research devices; and</text>
      </paragraph>
      <paragraph num="(11)">
        <text>Construct a replacement bulkhead within a maximum of 18 inches channelward of a functional bulkhead.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Term of License. An authorization under a general license expires 3 years after the date of issuance. If the construction or the activity authorized under this general license is not completed within 3 years, a license extension may not be granted by the Department and the licensee shall apply for a new license.</text>
    </paragraph>
    <paragraph num="D.">
      <text>General License Conditions. To obtain authorization under the general license to be valid, an applicant shall:</text>
      <paragraph num="(1)">
        <text>Obtain all required federal, State, county, or local approvals before beginning work on a licensed activity;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>When applicable, obtain an approved sediment and erosion control plan from the local soil conservation district before construction;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Notify the Enforcement Division of the Water Management Administration at least 5 days before beginning work;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Allow representatives of the Department to enter the property at reasonable times to inspect the ongoing or completed work under the license; and</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Design and construct the authorized work in a manner which minimizes adverse impacts on natural resource values, including water quality, plants, wildlife, and plant and wildlife habitat.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".05" heading="General Tidal Wetlands Permit.">
    <paragraph num="A.">
      <text>The Department shall issue a general wetlands permit to the Administration for those activities in private wetlands listed in §B of this regulation. A person proposing an activity in private tidal wetlands under the general wetlands permit shall apply to the Administration. The Administration shall consider the ecological, economic, developmental, recreational, and aesthetic values of the proposed project and determine if the project proposed in the application qualifies under the general wetlands permit. If a project qualifies under the general wetlands permit and does not require mitigation under COMAR 26.24.05.01, the Administration may issue the authorization directly to the applicant.</text>
    </paragraph>
    <paragraph num="B.">
      <text>General Wetlands Permit Projects. Projects which qualify for approval under the general permit include projects described in Regulation .04 of this chapter and projects to:</text>
      <paragraph num="(1)">
        <text>Install or maintain underground utilities such as phone, cable television, electricity, or natural gas pipelines not exceeding 12 inches in diameter if the surface of the wetlands is restored to its original elevation and vegetation;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Conserve soil, vegetation, water, fish, shellfish, and wildlife using best management practices; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Improve wildlife habitat as approved by the Administration.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Term of Permit. An authorization under the general permit expires 3 years after the date of issuance. If the construction or activity is not completed within 3 years, the Department may not grant an extension and the permittee shall reapply for authorization.</text>
    </paragraph>
    <paragraph num="D.">
      <text>General Permit Conditions. In order for an authorization under this general permit to be valid, the applicant shall meet the requirements under Regulation .04D of this chapter.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".06" heading="Conditions of a License or Permit.">
    <paragraph num="A.">
      <text>License Conditions. Standard conditions of a tidal wetlands license shall be imposed by the Board in accordance with COMAR 23.02.04.13.</text>
    </paragraph>
    <paragraph num="B.">
      <text>The Department may recommend that the Board include special conditions, including requirements for maintenance dredging, mitigation, compensation, and financial assurances, in accordance with COMAR 23.02.04.14. The Department shall use the guidelines in §§C—L of this regulation in recommending conditions to the Board.</text>
    </paragraph>
    <paragraph num="C.">
      <text>The licensee shall submit a construction schedule to the Department 10 days before the beginning of construction.</text>
    </paragraph>
    <paragraph num="D.">
      <text>The use of construction equipment or other temporary structural barriers may not decrease the width of the navigable waterway by more than 50 percent during construction, unless approved by the Department.</text>
    </paragraph>
    <paragraph num="E.">
      <text>The Department may prohibit dredging during certain times to protect shellfish. The Department may determine time restrictions in accordance with the following:</text>
      <paragraph num="(1)">
        <text>Factors including the type of project, nature of the bottom substrate, location, and other physical site characteristics of the site;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Mechanical dredging within 500 yards of shellfish areas is prohibited from December 16 through March 14, and June 1 through September 30; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Hydraulic dredging within 500 yards of shellfish areas is prohibited from June 1 through September 30.</text>
      </paragraph>
    </paragraph>
    <paragraph num="F.">
      <text>Dredge restrictions in other identified shellfish areas shall be determined on a case-by-case basis by the Department.</text>
    </paragraph>
    <paragraph num="G.">
      <text>Dredging may be prohibited during certain periods by the Department to protect identified finfish-spawning and nursery areas. The Department shall determine dredging time restrictions in accordance with the following:</text>
      <paragraph num="(1)">
        <text>Restrictions during the nursery period of finfish species shall be determined by the Department using factors including target species, type of project, location, and other physical site characteristics;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Dredging is prohibited from:</text>
        <paragraph num="(a)">
          <text>February 15 through June 15 in areas where yellow perch have been documented to spawn, and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>March 1 through June 15 in areas where other important finfish species identified by the Department have been documented to spawn.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="H.">
      <text>Dredging is prohibited within 500 yards of SAV from April 15 through October 15.</text>
    </paragraph>
    <paragraph num="I.">
      <text>Detailed final project plans and specifications shall be submitted to and approved by the Administration before the project begins.</text>
    </paragraph>
    <paragraph num="J.">
      <text>The Department may prohibit the construction of structures on, in, or over shore erosion control structures unless specifically licensed by the Board of Public Works.</text>
    </paragraph>
    <paragraph num="K.">
      <text>Other specific conditions may be recommended by the Department on a case-by-case basis.</text>
    </paragraph>
    <paragraph num="L.">
      <text>Permit Conditions.</text>
      <paragraph num="(1)">
        <text>Standard conditions of a private permit shall be imposed by the Department, which at a minimum address the following:</text>
        <paragraph num="(a)">
          <text>Protection of property rights;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Construction time period;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Term of permit;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Compliance with plans and specifications;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Maintenance of permitted project;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Protection and management of natural resources;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Use of navigable waters; and</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Other approvals required.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The Department may include special conditions such as requirements for maintenance dredging, mitigation, financial assurances, or other approvals. The Department shall use the guidelines in §B of this regulation in establishing special conditions.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".07" heading="License or Permit Modifications or Extensions.">
    <paragraph num="A.">
      <text>Requests for License or Permit Modifications.</text>
      <paragraph num="(1)">
        <text>Upon written request for a license or permit modification, the Department shall determine if the modification is major or minor.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Minor modifications to a license may be recommended to the Board or made to a permit by the Department if the modification involves:</text>
        <paragraph num="(a)">
          <text>A change in land ownership;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A reduction in the scope of the originally authorized work;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Revisions to the project plans or specifications that would otherwise be approved; or</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Structures, activities, or the conditions of a license or permit which require modification to correct adverse environmental impacts.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Major modifications to a license or permit require a new application as described in Regulation .02 of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Requests for Construction Period Extensions.</text>
      <paragraph num="(1)">
        <text>The Department may not extend the construction period for maintenance dredging projects.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The construction period of a tidal wetlands license or permit may be extended for a valid reason. Only one extension for construction authorized under a license or permit may be granted. An extension shall be for a period up to 3 years. A request for extension shall be made in writing to the Department and shall include the following:</text>
        <paragraph num="(a)">
          <text>The reason the project could not be completed within the construction period in the original license or permit;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Revised schedule for start and completion of construction;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Assurances that all other State, federal, and local approvals have not expired or have been authorized;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Evidence of a substantial effort made to construct the authorized works within the construction period specified in the license or permit;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Evidence that the project is to be constructed in phases over a number of years; or</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Evidence of undue hardship due to circumstances beyond the applicant's control.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Requests for Reinstatements. A wetlands license or permit that has expired may not be reinstated and requires a new application as described in Regulation .02 of this chapter.</text>
    </paragraph>
    <paragraph num="D.">
      <text>Modifications. If the Department determines that a modification to a project is necessary, the Department may revise a permit or request a revision of the license by the Board. If conditions are revealed which will not permit safe construction, the license or permit may be suspended or revoked in accordance with COMAR 26.24.01.06.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".08" heading="Appeals.">
    <paragraph num="A.">
      <text>License Decisions. A party aggrieved by a decision of the Board may petition the circuit court in the county where the land is located within 30 days after receiving the decision. An aggrieved party's impacted interests shall be specific and different from the interests of the public, and the right to an appeal is limited by law to aggrieved parties.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Permit Decisions.</text>
      <paragraph num="(1)">
        <text>An applicant who is adversely affected by a decision of denial, suspension, revocation, or condition of a permit by the Department may, within 30 days of receipt of the administrative action, file with the Director written exceptions and a request to present oral argument. After considering the written exceptions, the Director may hear argument and shall issue a written final decision.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The applicant, the county, or the municipal government where the land is located may appeal the final decision of the Director to the circuit court in the county where the land is located within 30 days of the final decision.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>An applicant may not reapply for a permit under this subtitle until after the expiration of 18 months from the date of the denial, or the final determination of an appeal from the denial.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <annotations>
    <annotation type="Authority">Environment Article, Title 16, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: February 14, 1994 (21:3 Md. R. 184)</annotation>
    <annotation type="History" subtype="Administrative History">(Wetlands regulations before February 14, 1994, appeared under COMAR 08.05.07)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .18B amended as an emergency provision effective August 1, 1995 (22:17 Md. R. 1309); amended permanently effective December 4, 1995 (22:24 Md. R. 1894)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .19A amended as an emergency provision effective August 1, 1995 (22:17 Md. R. 1309); amended permanently effective December 4, 1995 (22:24 Md. R. 1894)</annotation>
    <annotation type="History" subtype="Administrative History">Regulations .01—.08 were recodified from Regulations .03—.05, .18—.20, .23, and .26, respectively, under COMAR 08.05.05 Tidal Wetlands, June 1996</annotation>
  </annotations>