<?xml version='1.0' encoding='utf-8'?>
<chapter num="03" heading="Dredging and Filling" title_num="26" subtitle_num="24">
  <regulation prefix="Regulation" num=".01" heading="Maintenance Dredging.">
    <paragraph num="A.">
      <text>In addition to the requirements of COMAR 26.24.02.02, an applicant proposing to maintenance dredge, or to dredge to maintain an existing use, in State or private tidal wetlands shall submit the following information at the time of application:</text>
      <paragraph num="(1)">
        <text>A plan depicting the dimensions, including the existing and proposed depths and location of the main channel and all the spur channels proposed to be dredged;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Quantity of material to be dredged;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Documentation detailing when the site was last dredged and the dimensions of the channel, if applicable;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Evidence of historical boat use since January 1, 1972;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Texture characterization of material to be dredged; and</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Dredge material placement information in accordance with Regulation .03 or .05 of this chapter;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Except for emergency dredging projects as determined by the Department, a map depicting:</text>
        <paragraph num="(a)">
          <text>Current submerged aquatic vegetation populations within the area to be dredged, and a 500-yard buffer, if appropriate;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Date of the submerged aquatic vegetation survey;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Method of sampling; and</text>
        </paragraph>
      </paragraph>
      <paragraph num="(8)">
        <text>Justification for classifying the proposed maintenance dredging as an emergency.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>The Department may recommend that a wetland license contain a condition to allow for periodic maintenance dredging of quantities less than 500 cubic yards.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Dredging — General.">
    <paragraph num="A.">
      <text>Required Information. In addition to the requirements of Regulations .03 and .05 of this chapter and COMAR 26.24.02.02, an applicant proposing to perform dredging in State or private tidal wetlands that have never been dredged shall submit the following information at the time of application:</text>
      <paragraph num="(1)">
        <text>A description of the purpose for the dredging and a discussion of alternatives considered, including an evaluation of the no action alternative;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A plan of the proposed project, showing the:</text>
        <paragraph num="(a)">
          <text>Extent of the area to be dredged;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Existing and proposed depths;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Volume of material to be removed;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Extent of tidal wetlands to be impacted; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Identification of a dredged material disposal site;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The method of dredging and anticipated work schedule; and</text>
      </paragraph>
      <paragraph num="(4)">
        <text>A map depicting current submerged aquatic vegetation populations within and adjacent to the area to be dredged, date of the submerged aquatic vegetation survey, and the method of sampling.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Additional Information Requirements.</text>
      <paragraph num="(1)">
        <text>Based on project size and scope, environmental sensitivity of the project site, and potential adverse impacts to tidal wetlands, the Department may, with notice to the applicant by telephone, letter, or meeting, require information in addition to that in §A of this regulation. The Department recommends that an applicant consult with the Department before developing and submitting the information listed in §B(2)—(5) of this regulation.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A description of the predicted short-term and long-term impacts of dredging activities on water circulation, water quality, tidal wetland values, and aquatic biota may be required.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Bathymetric Survey.</text>
        <paragraph num="(a)">
          <text>A bathymetric survey of existing depths may be required.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The survey shall reflect current conditions in the area to be dredged and shall be dated.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The survey shall relate to mean low water (MLW) as 0.0 and be referenced to a recoverable vertical bench mark. Soundings may be poled or recorded by fathometer and shall be taken to an accuracy of 0.5 foot unless otherwise specified by the Department. The survey shall clearly identify low point elevations and shall extend 100 feet beyond the limits of the project or to the controlling depth contour in the adjoining waterway, whichever boundary leads to the larger survey area.</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Survey data shall be plotted on a grid at a minimum scale of 1 inch equals 100 feet with 1-foot contour intervals and spot elevations at a minimum of every 25 feet unless otherwise specified by the Department. The survey shall be referenced to two recoverable horizontal control points.</text>
        </paragraph>
        <paragraph num="(e)">
          <text>A bathymetric survey of the project area upon completion of the authorized dredging may be required.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>A plan drawing may be required that includes property lines and their bearings, bathymetric survey data, the proposed alignment and bearing of navigation channels or permanent structures that extend into State waters, and horizontal and vertical control points. The plan shall be certified by a registered professional engineer or registered land surveyor unless otherwise specified by the Department.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Provisions for monitoring and enhancing water quality may be required in accordance with applicable water quality standards established by the Department.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Design Guideline Requirements.</text>
      <paragraph num="(1)">
        <text>Dredging of channels, canals, and boat basins shall be designed to provide:</text>
        <paragraph num="(a)">
          <text>Adequate flushing and elimination of stagnant water pockets; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A demonstrated public benefit.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Navigational access projects shall when possible be designed to use piers to reach deep waters rather than to use dredging.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Navigational access channels to serve individual or small groups of riparian landowners shall be designed to prevent unnecessary channels. A central access channel with short spur channels shall be considered over separate access channels for each landowner.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Navigational access channels shall be designed to minimize alteration of State or private tidal wetlands. The channel shall provide a minimum width, length, and depth consistent with historic boating use or access.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The channel alignment shall make maximum use of natural or existing channels and bottom contours.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>The alignment of the channel shall first avoid and then minimize impacts to shellfish beds, submerged aquatic vegetation, and vegetated tidal wetlands. When feasible, the alignment shall be located the maximum distance feasible from shellfish beds, submerged aquatic vegetation, and other vegetated tidal wetlands.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>New Channels.</text>
        <paragraph num="(a)">
          <text>Channels through uplands, canals, or basins connecting to State waters for navigational access shall be considered only when the:</text>
          <paragraph num="(i)">
            <text>Applicant is a riparian landowner who demonstrates a need for access to State waters;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Proposed channel represents the smallest dimensions necessary to connect a basin created from upland, or is a public boat ramp to navigable waters if all other requirements of this subtitle are met; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Proposal is the best alternative means of providing reasonable access to navigable waters or no other alternative location exists that would cause less destruction or alteration of tidal wetlands.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>New channels shall be designed to comply with Maryland water quality standards and to avoid pockets of stagnant water having inadequate tidal flushing. The channel design shall include provisions for adequate water circulation.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Upland excavation that would open to State waters shall be performed in the dry and the banks shall be stabilized through wetland creation or the placement of stone before a connection to tidal waters is made.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(8)">
        <text>Provisions shall be included in the design for protection of the channel or canal banks against erosion by waves and boat wakes.</text>
      </paragraph>
      <paragraph num="(9)">
        <text>Dredging to obtain material for beach nourishment may be approved if an environmental analysis determines there will be no adverse impacts to the environment, and the requirements of Regulation .06 of this chapter are fulfilled.</text>
      </paragraph>
      <paragraph num="(10)">
        <text>Dredging for sand, gravel, or fill material may be approved when an environmental analysis determines that there will be no adverse impact on the environment, and no alternative fill material is available.</text>
      </paragraph>
      <paragraph num="(11)">
        <text>The use of explosives to create waterfowl potholes or to clear drainage blockages may be approved when an environmental analysis determines no significant impact to the surrounding habitat will occur, and when performed by a licensed expert.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Dredging Prohibitions for New Dredging Projects.</text>
      <paragraph num="(1)">
        <text>A person may not dredge for projects that are non-water-dependent.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A person may not dredge by means of a vessel's propeller.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>A person may not dredge in shallow water areas 3 feet or less at mean low water unless:</text>
        <paragraph num="(a)">
          <text>Historic boat use since January 1, 1972 is documented by:</text>
          <paragraph num="(i)">
            <text>Photographs showing the presence of a functional pier, boat, or mooring, and a written report from the applicant that describes the types of boats, their draft, and dates of use at the site;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>A navigational chart or a bathymetric survey, certified by a professional engineer or land surveyor licensed under Maryland law, that verifies the water depth;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>National Oceanic and Atmospheric Administration navigation charts;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>State and federal permits and licenses for dredging projects issued since January 1, 1972; or</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Other information considered appropriate by the Department;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>The proposed channel represents the smallest dimensions necessary to connect a basin created from upland, or a public boat ramp to navigable waters if all other requirements of this subtitle are met;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The proposed channel is necessary for construction of shore erosion control projects as described in COMAR 26.24.04.01;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The proposed channel is necessary for construction of navigational improvement projects such as jetties or breakwaters; or</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Otherwise determined by the Department.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="Upland Disposal of Dredged Material.">
    <paragraph num="A.">
      <text>Exemptions.</text>
      <paragraph num="(1)">
        <text>Previously Approved Disposal Facility. The requirements of §§B—C of this regulation may be waived for a dredge disposal facility previously approved by the Department if it can be demonstrated that the facility is capable of adequately containing the dredged material. Before authorizing the use of a previously approved upland disposal facility, the Department may require:</text>
        <paragraph num="(a)">
          <text>A written report stating that the facility is capable of accepting the volume of material to be dredged considering freeboard constraints, bulking, and remaining capacity;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>An evaluation regarding the safety and effectiveness of the facility to impound additional dredge material, and stability of outlet structures and embankments; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A currently approved soil conservation district plan.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Landfills. Use of an existing landfill may be approved by the Department, and the requirements of §§B—C of this regulation may be waived, if the licensee submits:</text>
        <paragraph num="(a)">
          <text>Documentation that the landfill proposed to be used is being operated in full compliance with local, State, and federal regulations; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Written approval from the landfill owner, or the owner's legal representative, accepting the quantity and type of material to be dredged.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Nonforested Upland Fields. Use of nonforested upland fields may be approved by the Department, and the requirements of §§B—C of this regulation may be waived, if:</text>
        <paragraph num="(a)">
          <text>The elevation of the dredge material is less than 3 feet in height; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The applicant submits:</text>
          <paragraph num="(i)">
            <text>An approved sediment and erosion control plan from the soil conservation district; and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Written approval from the property owner, or the owner's legal representative, accepting the quantity and type of material to be dredged.</text>
          </paragraph>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>General Requirements.</text>
      <paragraph num="(1)">
        <text>In addition to the requirements of Regulation .02 of this chapter and COMAR 26.24.02.02, an applicant proposing to dispose of dredged material on upland is required to submit the following information at the time of application:</text>
        <paragraph num="(a)">
          <text>Grain size analysis;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A detailed dredge disposal plan that includes the proposed disposal area and:</text>
          <paragraph num="(i)">
            <text>Property lines;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Existing and proposed topography and bathymetry;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Mean high water line;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Location of all tidal and nontidal wetlands and tributaries within 100 feet of any site disturbance;</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Limits of critical area buffers as defined in COMAR 27.01.09, COMAR 27.02.05, and the State-approved critical area program of a local jurisdiction;</text>
          </paragraph>
          <paragraph num="(vi)">
            <text>Stabilized access to the site;</text>
          </paragraph>
          <paragraph num="(vii)">
            <text>The method of dredge material transport to the disposal site, including the alignment of the pipe or the proposed route and staging areas as appropriate;</text>
          </paragraph>
          <paragraph num="(viii)">
            <text>Spillway location;</text>
          </paragraph>
          <paragraph num="(ix)">
            <text>Sediment and erosion control plan approval by the local soil conservation district; and</text>
          </paragraph>
          <paragraph num="(x)">
            <text>A vicinity map identifying the area to be dredged, and the surrounding land areas and water bodies within 100 feet of any disturbance;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>Proof of ownership or right to use the disposal site, including:</text>
          <paragraph num="(i)">
            <text>An executed deed conveying title of the site to the licensee;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>An executed easement;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Written consent of the landowner; or</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>A fully executed option agreement, long-term lease agreement, or contract sale of the site;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(d)">
          <text>Methods to ensure that water discharged from the disposal area does not adversely impact water quality, tidal wetlands, or aquatic habitat;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Methods to protect waters during construction operation and dewatering; and</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Methods to control or divert runoff and erosion from upland disposal sites.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Based on project size and scope, environmental sensitivity of the project site, potential adverse impacts to the environment, and the welfare and safety of the public, the Department may, with notice to the applicant by telephone, letter, or meeting, request the information in §C(1)—(5) of this regulation, in addition to other requirements of this subtitle. This information is required for all dredging projects proposing to dispose of hydraulically dredged material in a contained placement site. The Department recommends that an applicant consult with the Department before developing and submitting the following information listed in §C(1)—(5) of this regulation:</text>
      <paragraph num="(1)">
        <text>Composition of dredge material;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>An analysis of alternative disposal methods, including beneficial uses and site selection;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>A geotechnical evaluation or more detailed report prepared in support of the project which:</text>
        <paragraph num="(a)">
          <text>Demonstrates feasibility of the site for the intended use; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Provides geotechnical information regarding on-site soils intended for embankment construction, with the unified soil classification system being used to identify all materials intended for embankment construction,</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Provides geotechnical recommendations regarding the degree of embankment compaction to be achieved, design provisions to address hydrologic conditions at the site, and any other special provisions to address seepage control including the use of impermeable liners;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Identifies the location and results of all soil borings taken along the centerline of the proposed embankment and the area from which embankment material will be obtained, with a sufficient number of soil borings being taken to evaluate material quality and availability.</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Summarizes all geotechnical sampling information shown on the design plans including construction requirements that address unique surface and subsurface conditions of the site; and</text>
        </paragraph>
        <paragraph num="(f)">
          <text>References design standards;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>The type and settling characteristics of sediments to be dredged based upon the “Standard Method of Particle Size Analysis of Soils, AASHTO Designation T 88-90”, which is incorporated by reference as found in Standard Specifications for Transportation Materials and Methods of Sampling and Testing, Part II Tests, Fifteenth Edition, American Association of State Highway and Transportation Officials, (1990); and</text>
      </paragraph>
      <paragraph num="(5)">
        <text>A detailed plan including:</text>
        <paragraph num="(a)">
          <text>Notes related to vegetative stabilization, sediment and erosion control, and water quality;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Temporary and permanent vegetative stabilization specifications;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A detailed sequence of construction and operation;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>A water quality monitoring schedule;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Discharge return route to tidewater and outfall protection;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Drainage swales;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Utilities;</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Sediment and erosion controls;</text>
        </paragraph>
        <paragraph num="(i)">
          <text>Identified ecologic, archaeologic, or historic features;</text>
        </paragraph>
        <paragraph num="(j)">
          <text>Limits of disturbance and stockpile areas;</text>
        </paragraph>
        <paragraph num="(k)">
          <text>Cross section, height, and settlement of embankments;</text>
        </paragraph>
        <paragraph num="(l)">
          <text>Stage-storage curves or table;</text>
        </paragraph>
        <paragraph num="(m)">
          <text>Inflow point or points;</text>
        </paragraph>
        <paragraph num="(n)">
          <text>Outlet structures and the barrel location in the embankment;</text>
        </paragraph>
        <paragraph num="(o)">
          <text>Seepage controls;</text>
        </paragraph>
        <paragraph num="(p)">
          <text>Details and dimensions of dewatering structure;</text>
        </paragraph>
        <paragraph num="(q)">
          <text>Barrel type, size, and specifications and methods to obtain watertight joints;</text>
        </paragraph>
        <paragraph num="(r)">
          <text>Signature and seal by a professional engineer licensed to practice in Maryland;</text>
        </paragraph>
        <paragraph num="(s)">
          <text>Location of all subsurface borings;</text>
        </paragraph>
        <paragraph num="(t)">
          <text>Date of plan or plan revision; and</text>
        </paragraph>
        <paragraph num="(u)">
          <text>Soil conservation district approval.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="Guidelines for Upland Disposal of Dredged Material.">
    <paragraph num="A.">
      <text>Disposal sites shall be designed to have the least impact on:</text>
      <paragraph num="(1)">
        <text>Public safety;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Adjacent properties; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The environment.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Dredged Material Placement Facilities.</text>
      <paragraph num="(1)">
        <text>Dredged material placement facilities shall be designed with the specifications set forth in §B(2)—(12) of this regulation unless otherwise determined by the Department.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>All plans, reports, and supporting documentation shall be dated, sealed, and signed by a professional engineer licensed to practice in Maryland. All revisions shall be noted on the plans.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Soils shall be classified using the unified soil classification system.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The minimum top width of an embankment is as follows:</text>
        <paragraph num="(a)">
          <text>Less than 5 feet high embankment, top width = 4 feet;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>6—10 feet high, top width = 6 feet; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Greater than 10 feet, top width shall be determined by the engineer approving the design.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>A weir box and antiflotation devices shall have a minimum safety factor of 1.2.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>There shall be a minimum 2-foot freeboard to the settled top of an embankment.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Embankment cross-section side slopes dimensions shall be a minimum of 2 horizontal:1 vertical inside and 3 horizontal:1 vertical outside.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>The placement facility shall have a controlled overflow structure design that removes excess ponded water from the facility and that is capable of completely stopping the flow of any effluent. The weir overflow shall have an adjustable crest elevation to remove surface water while assuring that the effluent is in compliance with water quality requirements under COMAR 26.08.02—.04, as established by the Department.</text>
      </paragraph>
      <paragraph num="(9)">
        <text>The placement shall have a pipe outlet design that:</text>
        <paragraph num="(a)">
          <text>Specifies that the minimum size is 8 inches in diameter;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Includes measures to control scour and erosion;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Provides an outlet channel that withstands the maximum outlet velocity anticipated; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Provides watertight joints.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(10)">
        <text>Size of Disposal Facility.</text>
        <paragraph num="(a)">
          <text>The design of the disposal facility shall address effluent water quality based on surface area, embankment height, settling time, and sediment consolidation. When sizing the facility, allowances shall be incorporated in the design for ponding depth and freeboard requirements.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A stage-storage curve or table is required.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The size of the disposal facility shall be calculated using one of the procedures in §B(10)(d), (e), or (f) of this regulation.</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Formula:</text>
          <paragraph num="(i)">
            <text>V = (Qd)(B), where V equals total disposal volume required in cubic yards, Qd is the quantity of material to be dredged in cubic yards, and B is the bulking (expansion) factor.</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Figure 1 in §B(10)(d)(iii) of this regulation shall be used when selecting a bulking factor for hydraulic dredgings. A bulking factor of 1.4 shall be used for mechanical dredging.</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Figure 1 (Hydraulic Dredged Material Bulking Factors/Percent Passing #200 Sieve).</text>
          </paragraph>
        </paragraph>
        <paragraph num="(e)">
          <text>Size calculations may be made according to the “Confined Disposal of Dredged Material, EM 1110-2-5207, U. S. Army Engineer Waterways Experiment Station, Vicksburg, MS (1987)”, which is incorporated by reference.</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Size calculations may be made according to the “Environmental Effects of Dredging Technical Notes, Confined Disposal Guidance for Small Hydraulic Maintenance Dredging Projects-Design Procedures, EEDP-02-8, U. S. Army Engineer Waterways Experiment Station, Vicksburg, MS (December, 1988)”, which is incorporated by reference.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(11)">
        <text>Soils containing organic matter shall be rejected for use in the embankment of disposal facilities.</text>
      </paragraph>
      <paragraph num="(12)">
        <text>The design of the disposal facility shall include regulating provisions for the flow of dredge material into the basin or increasing the depth of ponded water at the overflow weir if the concentration of suspended solids in the effluent increases above acceptable limits.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Construction Requirements.</text>
      <paragraph num="(1)">
        <text>The Department may require that construction of a disposal facility:</text>
        <paragraph num="(a)">
          <text>Is under the supervision of a professional engineer licensed to practice in Maryland under Business Occupations and Professions Article, Title 14, Subtitle 3, Annotated Code of Maryland; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Meets all provisions of this subtitle.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Materials failing to meet specifications in this subtitle shall be removed.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Design changes shall be reported to the Department for approval in accordance with COMAR 26.24.02.07 before proceeding with construction.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>When construction of a disposal facility is complete, the Department may require submittal of a report that includes:</text>
        <paragraph num="(a)">
          <text>Date, location, and results of all material tests made;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Narrative of construction, including any problems and design changes; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>“As built” plans sealed and signed by a professional engineer licensed to practice in Maryland.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Conditions. Disposal facilities are prohibited in the critical area buffer unless approved in accordance with COMAR 27.01.03.04B, COMAR 27.02.05.04B, and a State-approved critical area program of a local jurisdiction.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".05" heading="Placement of Dredged Material in Open Water.">
    <paragraph num="A.">
      <text>Applicants proposing marsh creation or beach nourishment projects are exempt from the requirements of §B of this regulation.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Overboard Disposal.</text>
      <paragraph num="(1)">
        <text>In addition to the requirements of Regulation .02 of this chapter and COMAR 26.24.02.02, an applicant proposing overboard disposal of dredged material into open water is required to submit the information in §B(2)—(8) of this regulation at the time of application.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>An environmental study shall be submitted that includes measures to preserve or enhance the aesthetic, scenic, environmental, and natural resource values of the disposal site.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Test results of the physical and chemical parameters of the material to be dredged shall be submitted. Testing shall include physical characteristics of the material to be dredged, including material identification in accordance with the unified soil classification system and grain-size distribution.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Chemical characteristics, including the concentration of metals, organic compounds, oil and greases, nutrients, bacteria, and toxic compounds and their potential short-term and long-term release into the water column shall be submitted.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>A current bathymetric survey of the site where the proposed dredged material is to be placed, in accordance with the criteria of Regulation .02B(3) of this chapter, shall be submitted. In addition, the survey shall meet the following criteria:</text>
        <paragraph num="(a)">
          <text>Soundings shall be taken in sufficient quantity to clearly identify low point elevations within 500 feet beyond the limits of the proposed project; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Survey data shall be plotted at a scale not less than 1 inch equals 200 feet.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>A plan shall be submitted which depicts the following:</text>
        <paragraph num="(a)">
          <text>Adjacent land features;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Existing navigation channels;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Archaeological sites; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Permanent structures that extend into State waters.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(7)">
        <text>A hydrodynamic study of the impacts of the potential long-term movement of all material placed in tidal waters shall be submitted.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>A monitoring program shall be submitted that includes the collection and analysis of data before, during, and after the disposal operation, including:</text>
        <paragraph num="(a)">
          <text>Aquatic biota, including benthos, shellfish, and finfish;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Water quality parameters, including temperature, salinity, dissolved oxygen, conductivity, and pH;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Turbidity within the disposal site and specified adjacent areas;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Nutrients, including ammonia and phosphate;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>An assessment of volume reductions in the dredged material following placement, including sediment resuspension and transport through tidal and wave current interactions, fluid mud movement, and material consolidation; and</text>
        </paragraph>
        <paragraph num="(f)">
          <text>An assessment of the post-depositional benthos community recolonization.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Beneficial Uses of Dredged Material. Dredged material may be allowed for use in establishing substrate for marsh creation projects and beach nourishment projects, if the following parameters are met:</text>
      <paragraph num="(1)">
        <text>The dredged material is equal to or larger in size than sediments at the placement location, unless measures are taken to control its movement, including:</text>
        <paragraph num="(a)">
          <text>Breakwaters;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Groins; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Other similar structures;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The dredged material is relatively free of organic material; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>It can be documented that the site is properly suited to maintain the sediments placed at the site.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Design Guideline Requirements for Overboard Disposal and Beneficial Use of Dredged Material.</text>
      <paragraph num="(1)">
        <text>Proposed material placement may not cause adverse impacts to existing navigation channels, longshore current patterns, or adjacent properties.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Dredged material may not contain more than 10 percent silts and clays unless measures are taken to control the dredged material's movement as described in §C(1) of this regulation.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Floating debris or other objects shall be prevented from entering tidal waters.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Turbidity shall be minimized during the disposal operation.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Adverse impacts on fish spawning, nursery, and migration patterns shall be prevented.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Adverse impacts on commercial and sport fishing shall be minimized.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Adverse impacts on vegetated tidal wetlands, submerged aquatic vegetation, charted natural oyster bars, and anadromous fish spawning and nursery grounds shall be minimized.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".06" heading="Filling.">
    <paragraph num="A.">
      <text>In addition to the requirements of COMAR 26.24.02.02, an applicant proposing to fill State or private tidal wetlands for purposes other than shore erosion control as described in COMAR 26.24.04.01 shall submit an 8-1/2-inch by 11-inch site plan drawn to a minimum scale of 1 inch equals 100 feet depicting the following information:</text>
      <paragraph num="(1)">
        <text>Fill location referenced to existing landmarks;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Location of pilings and associated structures;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Existing topography and bathymetry that is referenced to mean low water;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Property lines;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Land use features;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Type of fill;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Surface water bodies including swales;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Location of all tidal and nontidal wetlands;</text>
      </paragraph>
      <paragraph num="(9)">
        <text>Mean high water line;</text>
      </paragraph>
      <paragraph num="(10)">
        <text>Utilities; and</text>
      </paragraph>
      <paragraph num="(11)">
        <text>A vicinity map that identifies the surrounding land areas and water bodies in the vicinity of the project.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Based on project size and scope, environmental sensitivity of the project site, and potential adverse impacts to tidal wetlands, the Department may, with notice to the applicant by telephone, letter, or meeting, require information in addition to that in §A of this regulation. The Department recommends that an applicant consult with the Department before developing and submitting the following information:</text>
      <paragraph num="(1)">
        <text>An alternatives analysis of the proposed project, including the “no action” and other alternatives that avoid and minimize adverse impacts on tidal wetlands, with the analysis including an evaluation of alternatives that have the least impact on public safety, adjoining properties, and the aquatic environment;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>An estimation of the public and private benefits from the project;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Additional site plan information, including;</text>
        <paragraph num="(a)">
          <text>Location of any submerged aquatic vegetation;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Location of shellfish beds;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Limits of critical area buffer as defined in COMAR 27.01.09.01;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Other significant ecological or historical features; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Location of all subsurface borings or other tests associated with any feasibility report prepared for the project;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Predicted impacts of the fill on tidal wetlands, water quality, and aquatic habitat, including leaching or dispersion of pollutants;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Methods to protect surface water and ground water from pollution;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>A statistical comparison between existing beach sediments and the proposed borrow material for beach nourishment and marsh creation projects;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Storm drain plans, details, and supporting documentation, reports, and design calculations;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Methods to control upland runoff; and</text>
      </paragraph>
      <paragraph num="(9)">
        <text>Methods to ensure that the fill does not adversely affect water quality during and after construction.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Reclamation of Lost Upland. Projects designed to reclaim lost upland by filling shall meet the following requirements:</text>
      <paragraph num="(1)">
        <text>A person who is the owner of land bounding on tidal water is entitled to reclaim upland lost by erosion or avulsion during the person's ownership of the land to the extent of provable boundaries;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The right to reclaim lost upland relates only to upland lost after January 1, 1972; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The burden of proof that the loss of upland occurred after January 1, 1972 is the responsibility of the owner of the land, and the riparian property owner may demonstrate the loss of upland through the use of historical photographs and land survey data.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Beach Nourishment. Beach nourishment projects shall meet the following requirements:</text>
      <paragraph num="(1)">
        <text>The fill material grain size shall be equal to or greater in grain size and character to the existing beach material, or determined otherwise to be compatible with existing site conditions and acceptable to the Department;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The fill material shall be relatively free of organic material, floating debris, or other objects;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Silt and clay fills that change the sandy nature of the existing beach materials are not acceptable;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Gravel fill may be acceptable, if particle sizes are equal to or greater than the existing beach materials; and</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Fill material shall be placed above the mean high water line before final grading to achieve the desired beach profile, unless site conditions prohibit the placement of fill material above the mean high water line and specific measures are designed to prevent material from washing away from the site.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Storm Drain Projects.</text>
      <paragraph num="(1)">
        <text>Exemptions. The following storm drain projects are exempt from the design guidelines of §E(2) of this regulation:</text>
        <paragraph num="(a)">
          <text>The extension of storm drains which directly discharge into tidal wetlands through new or replacement shore erosion control structures; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Storm drain projects which manage runoff from an individual lot with one dwelling.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Design Guidelines Requirements.</text>
        <paragraph num="(a)">
          <text>New storm drain systems shall be designed to manage the rate of runoff and improve water quality. At a minimum, a 10 percent improvement in water quality shall be achieved.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Storm drain systems shall:</text>
          <paragraph num="(i)">
            <text>Comply with applicable State or local design standards;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Be designed to follow natural drainage patterns and incorporate swales, filter strips, and sediment traps wherever feasible; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Include measures to prevent scouring from increased water velocities at their outlet.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>The licensee or permittee is responsible for the removal of any sediment deposited in the waters of the State as a result of the construction of an approved storm drain system or on-site grading and development activities.</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The licensee or permittee shall submit a preconstruction depth survey of any tidal wetlands within the project vicinity for approval by the Department before construction. The survey shall be referenced to mean low water at a fixed benchmark on the adjoining land, or an adjoining structure such as a bulkhead.</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The licensee or permittee shall submit a post-construction depth survey for review and verification by the Administration at any time after construction has begun, if required by the Administration. The survey shall be referenced to the same benchmark and elevation used for determining preconstruction depths.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <annotations>
    <annotation type="Authority">Environment Article, Title 16, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: February 14, 1994 (21:3 Md. R. 184)</annotation>
    <annotation type="History" subtype="Administrative History">(Wetlands regulations before February 14, 1994, appeared under COMAR 08.05.07)</annotation>
    <annotation type="History" subtype="Administrative History">Regulations .01—.06 were recodified from Regulations .06—.11, respectively, under COMAR 08.05.05 Tidal Wetlands, June 1996</annotation>
  </annotations>
</chapter>