  <regulation prefix="Regulation" num=".01" heading="Shore Erosion Control.">
    <paragraph num="A.">
      <text>The Department may not authorize an erosion control project if:</text>
      <paragraph num="(1)">
        <text>There is no evidence of erosion and the applicant is unable to document a claim of erosion;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Existing State or private tidal wetlands are effectively preventing erosion; or</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The proposed project may adversely affect:</text>
        <paragraph num="(a)">
          <text>An adjacent property;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Navigation, and the applicant has not adequately offset these impacts;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Threatened or endangered species, species in need of conservation, or significant historic or archaeological resources; or</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Natural oyster bars or private oyster leases.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>A person proposing a shoreline stabilization measure in State or private tidal wetlands that requires a wetlands license from the Board or a general wetlands license, wetlands permit, or general wetlands permit from the Department shall first consider:</text>
      <paragraph num="(1)">
        <text>No action; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Relocation of structures threatened by erosion.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Except as authorized under §E of this regulation, if the Department is satisfied that neither option listed under §B of this regulation is feasible, the person shall use a nonstructural shoreline stabilization measure.</text>
    </paragraph>
    <paragraph num="D.">
      <text>If a structural component is necessary in order to preserve the natural shore, minimize erosion, and establish aquatic habitat, a nonstructural shoreline stabilization measure may include the use of:</text>
      <paragraph num="(1)">
        <text>A breakwater, sand containment structure, or sill that is acceptable to the Department; or</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A beach that is acceptable to the Department, when used for the purpose of habitat enhancement.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>A person may use a structural shoreline stabilization measure:</text>
      <paragraph num="(1)">
        <text>In an area identified as appropriate for structural shoreline stabilization measures by the Department, in coordination with the Maryland Department of Natural Resources, and shown on a map approved by the Department under Regulation .01-1 of this chapter; or</text>
      </paragraph>
      <paragraph num="(2)">
        <text>At a site where the person has obtained a waiver from the Department in accordance with Regulation .01-2 of this chapter by demonstrating to the Department’s satisfaction that a nonstructural shoreline stabilization measure is not feasible.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".01-1" heading="Structural Shoreline Stabilization Maps.">
    <paragraph num="A.">
      <text>The Department shall develop and maintain maps on its website that:</text>
      <paragraph num="(1)">
        <text>Display the areas that are appropriate for structural shoreline stabilization measures; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Are readily available to the public.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>When determining the areas appropriate for structural shoreline stabilization measures, the Department shall consider:</text>
      <paragraph num="(1)">
        <text>The presence or absence of a natural shoreline;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Proximity to channels;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>As determined by the Department based on site conditions, the presence of high energy waves or a severely eroding shore that would render a nonstructural stabilization measure infeasible;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The extent to which a water-dependent facility requires a bulkheaded shoreline for loading and unloading operations, such as the berthing of commercial vessels;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Impacts to rare, threatened and endangered species, and species in need of conservation; and</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Any other site-specific factor, as determined relevant by the Department.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".01-2" heading="Nonstructural Shoreline Stabilization Waiver Process.">
    <paragraph num="A.">
      <text>A person who applies for a waiver from the requirement to construct a nonstructural shoreline stabilization measure under Regulation .01C of this chapter shall:</text>
      <paragraph num="(1)">
        <text>Use the form provided by the Department; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Complete the waiver process before submitting an application to obtain a wetlands license from the Board or a general wetlands license, wetlands permit, or general wetlands permit from the Department under COMAR 26.24.02.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>When evaluating a person’s request for a waiver, the Department shall determine whether the site is suitable to support a nonstructural shoreline stabilization measure by considering:</text>
      <paragraph num="(1)">
        <text>The width of the waterway;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The bottom elevation and slope at mean low water;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The bottom substrate:</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The fetch;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The bank elevation and orientation;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>The degree of erosion;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>The height and regularity of tides;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Any other physical constraints that would impede or prevent successful establishment of a nonstructural shoreline stabilization measure; and</text>
      </paragraph>
      <paragraph num="(9)">
        <text>Any other relevant environmental resources, including a Critical Area buffer and other plant, fish, and wildlife habitat, and the likely adverse or protective impact of a nonstructural shoreline stabilization measure on those resources in comparison to the likely adverse or protective impact of a structural shoreline stabilization measure on those resources.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>A person may obtain a waiver from the requirement to use a nonstructural shoreline stabilization measure if, to the Department's satisfaction, a structural shoreline stabilization measure is the only feasible alternative that will protect and maintain the person’s shoreline.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".01-3" heading="Application Requirements.">
    <paragraph num="A.">
      <text>In addition to the requirements of COMAR 26.24.02.02, a person proposing a shoreline stabilization measure shall submit the following information at the time of application:</text>
      <paragraph num="(1)">
        <text>An 8-1/2 by 11-inch plan, with dimensions, of the proposed project showing:</text>
        <paragraph num="(a)">
          <text>Location;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Land ownership;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Existing and proposed contours;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Existing mean high water line and, if applicable, existing landward boundary of State and private tidal wetlands, each as field-verified by the applicant;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>For a nonstructural shoreline stabilization measure, the proposed mean high water line and the proposed landward boundary of State and private tidal wetlands;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Existing and proposed structures, including:</text>
          <paragraph num="(i)">
            <text>A septic system;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>A utility-related structure;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>A building;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>A road;</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Drainage features; and</text>
          </paragraph>
          <paragraph num="(vi)">
            <text>An equipment storage area;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(g)">
          <text>Adjacent shoreline features;</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Best management practices to control any upland runoff which contributes to erosion;</text>
        </paragraph>
        <paragraph num="(i)">
          <text>Type of materials to be used in construction; and</text>
        </paragraph>
        <paragraph num="(j)">
          <text>Site bathymetry;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>A waiver, if the project qualifies for a structural shoreline stabilization measure under Regulation .01-2 of this chapter;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Photographs of the project site, the adjoining shoreline, and existing structures;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>In accordance with the requirements of COMAR 27.01.09.01-3, the proposed major or minor buffer management plan that will address disturbance of the buffer, including any disturbance to stabilize a bank or slope or to control erosion above mean high water;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Critical Area Buffer Notification Form signed by the property owner;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>If required by the Department, a design report that includes:</text>
        <paragraph num="(a)">
          <text>A foundation investigation;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A structural analysis;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The structural properties of the materials to be used to construct the proposed project;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The estimated economic, environmental, and other benefits to be derived from the project;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The design life expectancy of the project;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The sequence of construction;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>A description of the method of construction that includes:</text>
          <paragraph num="(i)">
            <text>Estimated beginning and completion dates;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The equipment to be used;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The proposed access to the site;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>The foundation excavations;</text>
          </paragraph>
          <paragraph num="(v)">
            <text>The means for diverting water away from the project during construction; and</text>
          </paragraph>
          <paragraph num="(vi)">
            <text>The means for controlling the dewatering discharges;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(h)">
          <text>Specific references and benchmarks used by the designer;</text>
        </paragraph>
        <paragraph num="(i)">
          <text>Estimated impact, if any, of the project on adjacent properties;</text>
        </paragraph>
        <paragraph num="(j)">
          <text>Estimated impact, if any, of the project on public access to the shore;</text>
        </paragraph>
        <paragraph num="(k)">
          <text>Written specifications for the quality of the materials and methods of construction to ensure that design criteria will be met or exceeded;</text>
        </paragraph>
        <paragraph num="(l)">
          <text>A description of how the reclamation of lost upland meets the requirements of COMAR 26.24.03.06C, if applicable; and</text>
        </paragraph>
        <paragraph num="(m)">
          <text>A description of measures to be taken to avoid and minimize impacts to plant, fish, and wildlife habitat before, during, and after construction; and</text>
        </paragraph>
      </paragraph>
      <paragraph num="(7)">
        <text>If required by the Department, an alternatives analysis, including:</text>
        <paragraph num="(a)">
          <text>The justification for rejecting the options required to be considered under COMAR 26.24.04.01B;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The justification for the selected shoreline stabilization measure; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>For a structural shoreline stabilization measure, proof of consideration of each alternative, including an analysis of habitat impact for each alternative, in the following order of preference:</text>
          <paragraph num="(i)">
            <text>Beach nourishment;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Breakwater;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Groin, jetty, or a similar structure;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Revetment; and</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Bulkhead.</text>
          </paragraph>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Based on project size and scope, environmental sensitivity of the project site, and potential adverse impacts to State or private tidal wetlands, the Department may, with notice to the applicant by telephone, letter, email, or meeting, require information in addition to §A of this regulation.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".01-4" heading="Design of Structural Shoreline Stabilization Measures.">
    <paragraph num="A.">
      <text>A person proposing a structural shoreline stabilization measure that employs a jetty, groin, breakwater, or other offshore structure, shall design the project to:</text>
      <paragraph num="(1)">
        <text>Allow natural littoral movement of sand along the shore;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Minimize erosion and undesirable shoaling;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Use materials that are:</text>
        <paragraph num="(a)">
          <text>Of adequate size, weight, and strength to function as intended;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Free of protruding objects, debris, and contaminants; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Selected to minimize impacts to water quality and plant, fish, and wildlife habitat;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Use backfill material free of litter, refuse, junk, metal, tree stumps, logs, or other unsuitable materials;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Prevent damage due to scour; and</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Minimize grading and other impacts on riparian habitat.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>The Department may not authorize encroachment into State or private tidal wetlands unless:</text>
      <paragraph num="(1)">
        <text>The encroachment is limited to that which is structurally necessary and is verified by a design report or other documentation, as required by the Department; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>For a bulkhead:</text>
        <paragraph num="(a)">
          <text>The encroachment is three feet or less beyond the mean high water line; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Other nonstructural and structural shoreline stabilization measures are infeasible, as determined by the Department.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Piers and Boathouses.">
    <paragraph num="A.">
      <text>Exemptions. Private noncommercial piers, boat hoists or lifts, mooring piles, and osprey poles that meet all of the following criteria are exempt from the requirement to obtain a license from the Board of Public Works or a license or permit from the Department under this subtitle:</text>
      <paragraph num="(1)">
        <text>Only one pier per property;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The width of the main section of the pier may not be greater than 6 feet;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Fixed or floating platforms, including Ts, Ls, and step-down platforms may not:</text>
        <paragraph num="(a)">
          <text>Exceed 200 square feet in area including the segment of the main pier section to which the platform is attached;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Be located over vegetated tidal wetlands, including submerged aquatic vegetation; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Be constructed on the landward 50 percent of the main pier section, except in canals and similar narrow water bodies as considered appropriate by the Department.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>The project may not include more than six mooring piles or create more than four boat slips;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The project may not include more than two osprey poles per property;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>A maximum of two, 3-foot wide finger piers not exceeding 50 percent of the proposed slip length may be constructed on the landward side of the end of a private pier;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>The project shall meet the minimum extended property line setback requirements established by the local jurisdiction in which the activity is proposed;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>The project may not be constructed in a location that will impede navigation or block ingress to and egress from adjoining properties;</text>
      </paragraph>
      <paragraph num="(9)">
        <text>The project may not obstruct the flow of the tide;</text>
      </paragraph>
      <paragraph num="(10)">
        <text>The pier may not extend within 100 feet of a ski course approved by the Department;</text>
      </paragraph>
      <paragraph num="(11)">
        <text>The pier may not extend more than 100 feet channelward of the tidal wetlands boundary line, or a distance of 25 percent of the width of the waterway, whichever is less;</text>
      </paragraph>
      <paragraph num="(12)">
        <text>Piers over vegetated tidal wetlands shall be constructed a minimum of 3 feet above the wetlands; and</text>
      </paragraph>
      <paragraph num="(13)">
        <text>The owner or owner's agent shall notify the Department on a form provided by the Department within 10 days before construction of the pier or any auxiliary structure.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Pier Criteria.</text>
      <paragraph num="(1)">
        <text>The Department may issue, deny, modify, or condition a license in accordance with COMAR 26.24.01.03 for the construction of fixed or floating piers, decks, walkways, and related structures. The Department may not issue a license for a fixed or floating pier, deck, walkway, or related structure which adversely affects shallow water habitat, submerged aquatic vegetation, shellfish, or vegetated tidal wetlands. The Department shall use all the criteria in §B(2)—(4) of this regulation in making final decisions on fixed or floating piers, decks, walkways, or other related structures not exempted in COMAR 26.24.02.01C(7) and §A of this regulation.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Private Noncommercial Piers.</text>
        <paragraph num="(a)">
          <text>The main section of a pier may not be wider than 6 feet.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A pier shall meet the minimum extended property line set-back requirements established by the local jurisdiction in which the activity is proposed.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A pier may not:</text>
          <paragraph num="(i)">
            <text>Be constructed in a location that will impede navigation or block ingress and egress to adjoining properties;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Obstruct the flow of the tide;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Extend within 100 feet of a ski course approved by the Department;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Extend more than 25 percent across a waterway unless it is determined by the Department that the pier will not adversely affect navigation, recreation, aesthetics, or the biological character of the area; or</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Include more than six mooring piles, four boat lifts or hoists, or four boat slips.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(d)">
          <text>Piers over vegetated tidal wetlands shall be constructed a minimum of 3 feet above the wetland substrate.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Private, Noncommercial Pier Platforms. The total area of fixed or floating platforms such as Ts and Ls, and step-down platforms:</text>
        <paragraph num="(a)">
          <text>Shall include the segment of the main pier section to which the platform is attached and may not exceed 200 square feet;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>May not be located over vegetated tidal wetlands, including submerged aquatic vegetation; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>May not be constructed on the landward 50 percent of the main pier except in canals and other similar narrow water bodies as deemed appropriate by the Department.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Private, Noncommercial Finger Piers. Two, 3-foot wide finger piers may be constructed on the landward side of the end of the main pier. Finger piers may be constructed in addition to other fixed or floating platforms and may not be included in calculating the area for purposes of the exemption in §A(3) of this regulation.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Boathouses.</text>
      <paragraph num="(1)">
        <text>Routine repair and maintenance of existing boathouses is exempt under COMAR 26.24.02.01C(5) if there is no increase in width, length, height, or channelward encroachment.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Except at commercial marinas, a person may not construct a new boathouse in or over State or private wetlands.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Appeals. A person aggrieved by a final decision of the Administration may appeal the decision in accordance with COMAR 26.24.02.08.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="Marinas.">
    <paragraph num="A.">
      <text>In addition to the requirements of COMAR 26.24.02.02, an applicant for a new marina or marina expansion is required to submit the following information at the time of application:</text>
      <paragraph num="(1)">
        <text>An alternatives analysis, including the alternative of no action, with the potential impacts on water quality, tidal wetland values, and aquatic habitat discussed for each alternative for:</text>
        <paragraph num="(a)">
          <text>Marina location;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Construction methods;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Configuration of project components;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Dimensions; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Related facilities;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>A bathymetric survey of the proposed marina site;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>A description of the marina facility, including the number of slips, breakwaters, or jetties;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>A description of:</text>
        <paragraph num="(a)">
          <text>Marina support facilities including:</text>
          <paragraph num="(i)">
            <text>Parking;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Storm water management facilities;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Concessions;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Boat sales;</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Boat repair;</text>
          </paragraph>
          <paragraph num="(vi)">
            <text>Hauling;</text>
          </paragraph>
          <paragraph num="(vii)">
            <text>Dry storage;</text>
          </paragraph>
          <paragraph num="(viii)">
            <text>Sewage pumpout facilities;</text>
          </paragraph>
          <paragraph num="(ix)">
            <text>Utilities;</text>
          </paragraph>
          <paragraph num="(x)">
            <text>Swimming pools;</text>
          </paragraph>
          <paragraph num="(xi)">
            <text>Restaurants; and</text>
          </paragraph>
          <paragraph num="(xii)">
            <text>Lodging facilities; and</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>Techniques to minimize the adverse environmental impacts of the facilities in §A(4)(a) of this regulation;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>A description of the impact of the marina on State or federal navigation channels located within 3,000 feet of the project;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>A description of the existing site characteristics, including water quality in the project area;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Location of materials such as submerged cables, piles, pipelines, or debris to be removed during construction, as well as measures for disposal;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Location of boat repair, cleaning, wet and dry storage facilities, fueling facilities, and other boat service facilities;</text>
      </paragraph>
      <paragraph num="(9)">
        <text>The location of the areas in which antifouling compounds for boat bottom painting, waste oil, washwater, and other pollutants are used;</text>
      </paragraph>
      <paragraph num="(10)">
        <text>A description and plan of the method proposed to manage water quality associated with storm water runoff; and</text>
      </paragraph>
      <paragraph num="(11)">
        <text>A flushing study for basins dredged into upland.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>If the proposed new marina or marina expansion includes dredging and dredge disposal, the information requirements and design guidelines in COMAR 26.24.03.02—.05 shall be met.</text>
    </paragraph>
    <paragraph num="C.">
      <text>Based on project size and scope, environmental sensitivity of the project site, and potential adverse impacts to tidal wetlands, the Department may, with notice to the applicant by telephone, letter, or meeting, require information in addition to §§A and B of this regulation. The Department recommends that an applicant consult with the Department before developing and submitting the following information:</text>
      <paragraph num="(1)">
        <text>The predicted short-term and long-term direct and indirect impacts on water quality, tidal wetland values, and aquatic habitat;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Increased noise levels, boat wakes, pollutant loading, and other project-related impacts;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Possible interference with water currents and impacts on littoral drift, sediment deposition, and shoaling;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Impacts on water circulation and flushing within the project area;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Other alterations of tidal wetlands and the impact on biological productivity;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Schedules, monitoring programs, or other provisions to be used during construction, operation, and maintenance to reduce or avoid adverse environmental impacts and to keep erosion, turbidity, and siltation at the lowest possible levels;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Special provisions to be used to enhance the environment;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>The long-term public gain expected from the project such as:</text>
        <paragraph num="(a)">
          <text>Employment;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Tax yields;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Reduction of existing pollution; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Enhancement of public access to the water;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(9)">
        <text>Estimated frequency of maintenance dredging, the volume of materials to be dredged over the life of the project, and site or sites to be used for disposal of these materials;</text>
      </paragraph>
      <paragraph num="(10)">
        <text>A description of how the speed, numbers, and directional movements of boat traffic will:</text>
        <paragraph num="(a)">
          <text>Be controlled in and out of the marina;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Impact commercial navigation; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Impact boats kept at the proposed marina facility, with the techniques to minimize the adverse impact of boat wakes on the proposed facility being addressed; and</text>
        </paragraph>
      </paragraph>
      <paragraph num="(11)">
        <text>A plan to minimize oil spillage into the basin and to identify contingencies for oil spill containment and removal.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Pumpout Facilities.</text>
      <paragraph num="(1)">
        <text>A person may not construct additional slips at an existing property that would result in a total capacity of more than ten slips or construct a new marina with more than ten slips unless:</text>
        <paragraph num="(a)">
          <text>The marina has a wastewater collection and treatment system that is adequate to handle any existing and proposed flows and is approved by the local health department;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>There is a pumpout station on-site that is adequate to handle the increased sewage capacity from vessels that use the marina and that is operable and accessible at reasonable times; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The marina has a contract with a pumpout facility that is:</text>
          <paragraph num="(i)">
            <text>Located not more than 2 miles from the marina;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Adequate to handle the increased sewage capacity from vessels that use the marina, as determined by the local health department; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Operable and accessible at reasonable times.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Wastewater collection and treatment facilities may be required, in consultation with the Department, if the marina:</text>
        <paragraph num="(a)">
          <text>Has a capacity of more than 25 slips;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Has a capacity of ten or more slips that are designed to accommodate boats of 25 feet or more in length; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Is located off the main stem of the major river tributaries of the Chesapeake Bay and coastal bays or in sensitive areas identified for no pollutant discharge by the State.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Vessel Mooring Facilities. The placement of buoys, group mooring buoys, and other apparatus used to secure, berth, or moor vessels in the waters of the State shall conform to the requirements of COMAR 08.04.13.</text>
    </paragraph>
    <paragraph num="F.">
      <text>Marina Management Plan. The location of all new marinas or expansion of an existing marina shall be consistent with a marina management plan, if any, that has been approved by the local government. If there is a conflict between a local marina management plan and this subtitle, the more stringent regulation takes priority.</text>
    </paragraph>
    <paragraph num="G.">
      <text>Marina Siting Guidelines.</text>
      <paragraph num="(1)">
        <text>New marina development and the expansion of existing marinas shall be located:</text>
        <paragraph num="(a)">
          <text>To avoid and minimize impacts to tidal wetlands and other aquatic resources; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>On waterways with strong flushing characterized by:</text>
          <paragraph num="(i)">
            <text>A bottom which slopes from headwaters to mouth without sumps or other features which inhibit complete water exchange;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The waterway has an unconstricted entrance; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The waterway has few branches, coves, and other features which inhibit complete mixing.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>New marina development and expansion of existing marinas may not be located in areas where:</text>
        <paragraph num="(a)">
          <text>The natural depth is 4.5 feet or less at mean low water unless the marina basin is excavated from upland; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Their presence would adversely impact submerged aquatic vegetation, productive macroinvertebrate communities, shellfish beds, fish spawning or nursery areas, rare, threatened, or endangered species, or species in need of conservation, or historic waterfowl staging areas.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Expansion of existing marinas is favored over development of new marinas.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="Conduits, Cables, Pipes, or Other Crossings of State Tidal Wetlands.">
    <text>The construction, reconstruction, alteration, or addition to any conduit, cable, pipeline, intake or discharge pipe, trestle, or other similar device, structure, or apparatus, over, on, in, or under State tidal wetlands or waters of the State requires a license. A license issued for this construction is subject to the compensation requirements of COMAR 23.02.04 as may be assessed by the Board.</text>
  </regulation>
  <annotations>
    <annotation type="Authority">Environment Article, Title 16, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: February 14, 1994 (21:3 Md. R. 184)</annotation>
    <annotation type="History" subtype="Administrative History">(Wetlands regulations before February 14, 1994, appeared under COMAR 08.05.07)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .14 amended as an emergency provision effective August 1, 1995 (22:17 Md. R. 1309); amended permanently effective December 4, 1995 (22:24 Md. R. 1894)</annotation>
    <annotation type="History" subtype="Administrative History">Regulations .01—.04 were recodified from Regulations .12, .14, .16, and .17, respectively, under COMAR 08.05.05 Tidal Wetlands, June 1996</annotation>
    <annotation type="History" subtype="Administrative History">Chapter revised as an emergency provision effective March 9, 2007 (34:7 Md. R. 695); emergency expired September 5, 2007</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01 repealed and new Regulation .01 adopted effective February 4, 2013 (40:2 Md. R. 73)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01-1 adopted effective February 4, 2013 (40:2 Md. R. 73)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01-2 adopted effective February 4, 2013 (40:2 Md. R. 73)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01-3 adopted effective February 4, 2013 (40:2 Md. R. 73)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01-4 adopted effective February 4, 2013 (40:2 Md. R. 73)</annotation>
  </annotations>
</chapter>