<?xml version='1.0' encoding='utf-8'?>
<chapter num="05" heading="Mitigation" title_num="26" subtitle_num="24">
  <regulation prefix="Regulation" num=".01" heading="Mitigation.">
    <paragraph num="A.">
      <text>Goal. It is the goal of the State to preserve tidal wetlands, prevent their loss and despoliation, and strive for a net resource gain in tidal wetlands acreage and function.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Mitigation Requirements.</text>
      <paragraph num="(1)">
        <text>An applicant for a license or permit shall design a project to first avoid and then minimize the loss of tidal wetlands. If an applicant demonstrates that alteration of tidal wetlands cannot be avoided to accomplish the project, the Department shall:</text>
        <paragraph num="(a)">
          <text>Recommend that the Board require mitigation as a condition of a State tidal wetlands license; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Require mitigation as a condition of a private tidal wetlands permit.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Mitigation projects shall be designed to replace the values and functions associated with the wetlands to be impacted.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Mitigation projects shall be connected to existing tidal wetlands or tidal waterways. Projects may be located on multiple parcels. Projects shall be located according to the following geographic location in order of preference, unless otherwise determined by the Department:</text>
        <paragraph num="(a)">
          <text>Locations on-site;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Locations off-site in the:</text>
          <paragraph num="(i)">
            <text>Immediate watershed subsegment where the tidal wetland loss occurred,</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Watershed sub-basin where the tidal wetland loss occurred, or</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>State minor basin where the tidal wetlands loss occurred.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Mitigation for the loss of tidal wetlands shall be considered in the following order of preference:</text>
        <paragraph num="(a)">
          <text>Restoration;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>In-kind creation;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Out-of-kind creation;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Enhancement of existing tidal wetlands;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Monetary compensation to the Wetlands Compensation Fund.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>Enhancement activities may be accepted in addition to tidal wetlands restoration or creation when the applicant has demonstrated to the satisfaction of the Department that enhancement provides additional protection or improves tidal wetlands functions. Activities may include:</text>
        <paragraph num="(a)">
          <text>Enhancement of degraded tidal wetlands; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Preservation of existing tidal wetlands.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>The Department may recommend that the Board accept monetary compensation only if the Department determines that creation, restoration, or enhancement of tidal wetlands are not feasible alternatives.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Mitigation requirements may be reduced or eliminated:</text>
        <paragraph num="(a)">
          <text>For shore erosion control projects that meet all of the requirements of COMAR 26.24.04.01; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>If the proposed project provides a significant environmental benefit as determined by the Department.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(8)">
        <text>The Department may not base a final tidal wetland permit decision or tidal wetland license recommendation solely on the environmental benefits of a mitigation proposal or the financial benefits of a monetary compensation proposal.</text>
      </paragraph>
      <paragraph num="(9)">
        <text>The Department may approve mitigation bank sites in consultation with the appropriate local, State, and federal agencies.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Standards.</text>
      <paragraph num="(1)">
        <text>The Department may use acreage replacement ratios to determine the size of newly created, restored, or enhanced tidal wetlands as mitigation for the loss of existing tidal wetlands. Acreage replacement ratios are expressed as a relationship between two numbers. The first number is the acreage of tidal wetlands to be mitigated and the second is the acreage of tidal wetlands lost. Acreage replacement ratios for in-kind creation and restoration are as follows:</text>
        <paragraph num="(a)">
          <text>Open water tidal wetlands—1:1;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Emergent tidal wetlands—2:1;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Scrub-shrub tidal wetlands—2:1;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Forested tidal wetlands—2:1; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Tidal wetlands habitat for rare, threatened, or endangered species, or species in need of conservation—3:1.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Out-of-kind creation and enhancement ratios are increased by a factor of 2.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>A mitigation project, as built, shall meet the following plant survival criteria:</text>
        <paragraph num="(a)">
          <text>After 5 years, greater than 85 percent of the mitigation site shall be vegetated by planted species approved by the Department; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Allowances shall be made for natural species changes as long as the plant communities are similar to those lost.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>In determining if mitigation activities will replace tidal wetlands acreage and functional losses, the Department shall consider the following:</text>
        <paragraph num="(a)">
          <text>Degree to which the mitigation activity replaces the functions of the lost tidal wetlands;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Benefits of the mitigation activity in rehabilitating or maintaining tidal wetlands;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Scope and extent of the mitigation activity;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Proximity of the mitigation activity to the tidal wetlands loss;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Technical merits of the mitigation activity and its likelihood of long-term success;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Adverse impact of the mitigation activity on natural resources;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Relationship of the mitigation activity to ongoing natural resource management activities; and</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Compatibility of the mitigation activity with approved comprehensive river or watershed management plans, if applicable.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Mitigation Plan.</text>
      <paragraph num="(1)">
        <text>At a minimum, a mitigation plan shall contain the following information:</text>
        <paragraph num="(a)">
          <text>A plan view of the mitigation area drawn at a scale not smaller than 1 inch equals 50 feet, including the delineation of all existing and adjacent tidal and nontidal wetlands, submerged aquatic vegetation, and shellfish resources;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Existing and proposed elevations of the ground contours referenced to mean low water at the site;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Cross-section views if elevation changes are required to provide adequate substrate to support plant species;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The location and description of all existing and proposed tidal wetlands plants by species;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Photographs of the affected tidal wetlands, including the types of vegetation;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The proposed method of construction, including temporary or permanent access roads;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Location, type, and characteristics of all borrow or fill materials and method of site grading;</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Construction schedule;</text>
        </paragraph>
        <paragraph num="(i)">
          <text>Method of final site stabilization;</text>
        </paragraph>
        <paragraph num="(j)">
          <text>A description of how the proposed mitigation project will replace the functions of lost tidal wetlands; and</text>
        </paragraph>
        <paragraph num="(k)">
          <text>Monitoring plan.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>A licensee or permittee shall implement the mitigation plan before or concurrent with the construction of the project unless otherwise directed by the Department.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>A bond shall be recommended as a condition of a license or required as a permit condition to assure that mitigation is performed. The Department shall approve the form of the bond in accordance with Regulation .02 of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Monitoring Report.</text>
      <paragraph num="(1)">
        <text>A permittee or licensee shall submit annual monitoring reports for 5 years from the completion of the construction of the mitigation project, unless the permittee or licensee has received written notice from the Department that the monitoring requirements have been fulfilled in less than 5 years. The monitoring report shall include the following:</text>
        <paragraph num="(a)">
          <text>A description of how the mitigation project meets the mitigation project standards in this regulation;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Photographs of the mitigation project;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The commercial source of planting stock whenever planting is required;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>A description of modifications which have been made or need to be made to implement the mitigation plan necessary to meet this regulation; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>An “as-built” site design plan shall be included in the first annual report, and subsequent reports shall detail any modifications to the “as built” plan.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The Department reserves the right to inspect the mitigation project at any reasonable time during the construction and required monitoring period, and any time after that to assess the long-term viability of the mitigation site.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Through written notification to the permittee or licensee, the Department may extend the required monitoring period for not more than an additional 3-year period, for a total of 8 years, if the mitigation project fails to comply with the standards in §C of this regulation.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Bonding for Mitigation Purposes.">
    <paragraph num="A.">
      <text>This regulation does not apply to any State, county, or municipal government, or to projects licensed by the Board.</text>
    </paragraph>
    <paragraph num="B.">
      <text>This regulation only applies to those projects proposed and permitted by the Department in private tidal wetlands.</text>
    </paragraph>
    <paragraph num="C.">
      <text>The bond is payable to the Department and conditioned upon fulfillment of mitigation monitoring requirements.</text>
    </paragraph>
    <paragraph num="D.">
      <text>Alternative Forms of Security.</text>
      <paragraph num="(1)">
        <text>Instead of a surety bond, the Department may accept one of the following forms of security:</text>
        <paragraph num="(a)">
          <text>A deposit of cash or negotiable bonds of the federal government having a market value equal to the bond amount accompanied by a written agreement of the bank to pay the State on demand in the event of forfeiture;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A certificate of deposit equal to the required bond amount, issued by a bank in the State and with a written agreement from the bank to pay the State on demand in the event of forfeiture;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>An irrevocable letter of credit equal to the bond amount, issued by a bank or financial institution organized to do business in the State, that expressly states that the total sum is guaranteed to be available and payable directly to the State on demand in the event of forfeiture;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The grant to the Department, in trust, of a deed, easement, or other interest in upland property owned by the permittee that has the same or greater monetary value than the selected mitigation site; or</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Fulfillment of mitigation requirements before completion of the permitted activity which results in the loss of tidal wetlands.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The permittee shall submit to the Department the alternative form of security under this regulation, until authorized by the Department for release. Alternative forms of security may not be released until monitoring of the mitigation project has been successfully completed.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Amount of Bond.</text>
      <paragraph num="(1)">
        <text>The amount of the bond for a permittee is $50,000 per acre of tidal wetlands mitigation required under the permit, or in an amount determined by the Department.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The permittee may request reduction of the bond amount by submitting a written request to the Department with a justification for reducing the bond amount, including estimated or actual costs to complete the mitigation project, and any other relevant information.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The Department shall determine whether a lesser amount is sufficient to cover the cost of the mitigation project, taking into account the following:</text>
        <paragraph num="(a)">
          <text>Number of acres to be mitigated;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The cost of land in the area of the mitigation site;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The proposed method of mitigation; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Any other relevant factors, including the likelihood of success of the project.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="F.">
      <text>Liability under the bond continues until the Department determines that the monitoring requirements have been fulfilled, and the surety or financial institution receives written notice from the Department that the mitigation project was successfully completed.</text>
    </paragraph>
    <paragraph num="G.">
      <text>A surety bond or other alternative form of security may be cancelled by the surety, bank, or other issuing entity when both of the following conditions are satisfied:</text>
      <paragraph num="(1)">
        <text>The surety notifies the Department and the permittee of its intent to cancel the bond, in writing, by certified mail, not less than 90 days before cancellation; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>At least 45 days before the cancellation date indicated in the notice, the permittee files a replacement bond from a surety, bank, or other issuing entity to provide a substitute security which will be effective on the cancellation date indicated in the notice.</text>
      </paragraph>
    </paragraph>
    <paragraph num="H.">
      <text>Bond Forfeiture.</text>
      <paragraph num="(1)">
        <text>The bond or other instrument securing compliance with the mitigation plan may be subject to forfeiture upon:</text>
        <paragraph num="(a)">
          <text>Revocation of a tidal wetlands license or permit;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Failure to comply with an administrative order; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Failure to comply with any element of the approved mitigation plan.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The Department, in writing and by certified mail, shall notify the permittee, surety, or other financial institution of the Department's intention to initiate forfeiture proceedings and the grounds for forfeiture.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The permittee, surety, or other financial institution has 30 days from receipt of the notice of forfeiture to show cause why the bond or other instrument may not be forfeited.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>On showing cause, the Department shall provide for a reasonable time for the permittee, surety, or other financial institution to correct the problem.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>If the permittee, surety, or other financial institution fails to show cause, the bond is forfeited nisi and the Department shall notify the permittee, surety, or other financial institution. If a showing of an intention to correct the problem in compliance with the mitigation plan is not submitted within 30 days from forfeiture nisi, the bond shall be forfeited absolute.</text>
      </paragraph>
    </paragraph>
    <paragraph num="I.">
      <text>If tidal wetlands are adequately protected, the Department may allow an applicant to post one bond under Environment Article, §15-823, Annotated Code of Maryland, or another Department program requiring bonding.</text>
    </paragraph>
    <paragraph num="J.">
      <text>A permittee may not conduct a regulated activity in a tidal wetland if the permittee previously forfeited a bond under this subtitle, unless the permittee repays the Department the cost of completing the mitigation project in excess of the forfeited bond, plus interest at the rate set in Courts and Judicial Proceedings Article, §11-107(a), Annotated Code of Maryland. If the mitigation project is still not completed, the permittee shall complete the mitigation project at the permittee's expense according to the approved mitigation plan.</text>
    </paragraph>
  </regulation>
  <annotations>
    <annotation type="Authority">Environment Article, Title 16, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: February 14, 1994 (21:3 Md. R. 184)</annotation>
    <annotation type="History" subtype="Administrative History">(Wetlands regulations before February 14, 1994, appeared under COMAR 08.05.07)</annotation>
    <annotation type="History" subtype="Administrative History">Regulations .01 and .02 were recodified from Regulations .21 and .22, respectively, under COMAR 08.05.05 Tidal Wetlands, June 1996</annotation>
  </annotations>
</chapter>