<?xml version='1.0' encoding='utf-8'?>
<regulation prefix="Regulation" num=".04" citation="COMAR 27.03.01.04" title_num="27" subtitle_num="03" chapter_num="01" heading="Categories of Applications to be Submitted to the Executive Director.">
  <paragraph num="A.">
    <text>A local jurisdiction shall electronically submit to the Executive Director each application for:</text>
    <paragraph num="(1)">
      <text>A variance from the local Critical Area program;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>In the resource conservation area:</text>
      <paragraph num="(a)">
        <text>A site plan;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>A subdivision;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>A lot consolidation or a reconfiguration;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>A special exception;</text>
      </paragraph>
      <paragraph num="(e)">
        <text>A conditional use; and</text>
      </paragraph>
      <paragraph num="(f)">
        <text>A zoning map amendment or a rezoning.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>In an intensely developed area or a limited development area, a subdivision or a lot consolidation or reconfiguration:</text>
      <paragraph num="(a)">
        <text>That proposes impacts to any habitat protection area, including the buffer; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>On a site that has received growth allocation; and</text>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>In accordance with COMAR 27.01.14 and COMAR 27.02.07, a major or minor solar energy generating system that would be located wholly or partially in a limited development area or a resource conservation area..</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>The local approving authority shall electronically submit to the Executive Director final approvals for:</text>
    <paragraph num="(1)">
      <text>A major solar energy generating system; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>In accordance with COMAR 27.01.04.03 and 27.01.09.01-3, for each category of application under §A(1)—(3) of this regulation;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Upon request by the Executive Director, a major buffer management plan; and</text>
    </paragraph>
    <paragraph num="(4)">
      <text>As applicable, each completed Commission form entitled “Shoreline Stabilization Measure Buffer Management Plan.”.</text>
    </paragraph>
  </paragraph>
</regulation>