  <paragraph num="A.">
    <text>A facility operator shall commence operation of video lottery terminals in a permanent facility within 18 months after the date the Commission issues an operation license.</text>
  </paragraph>
  <paragraph num="B.">
    <text>The permanent facility must be located at the location for which the Video Lottery Facility Location Commission awarded a video lottery operation license.</text>
  </paragraph>
  <paragraph num="C.">
    <text>The Commission may approve an extension of time for the commencement of operations if:</text>
    <paragraph num="(1)">
      <text>A facility operator submits a written request for an extension; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The Commission determines that extenuating circumstances exist that are beyond the control of the facility operator which have prevented the facility operator from complying with §A of this regulation.</text>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>The Commission may:</text>
    <paragraph num="(1)">
      <text>Approve an extension of 6 months to comply with §A of this regulation; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Not grant more than two extensions to a facility operator.</text>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>If a facility operator fails to comply with the requirements of this regulation, its operation license shall be revoked and shall automatically revert to the State.</text>
  </paragraph>